planning report MCU19-0016
Figure 6: Picture from walkway looking northwest (56 Seaview adjoining)
3.0 Proposed development details
Table 3: Summary of development aspects
Material change of use
Building height 7.9m
Site coverage Lower Ground Level – 28%
Ground Level – 37%
First Level – 12%
Overall = 38%
Car parking Double garage
Site access New residential driveway to Seaview Tce with the existing
9m wide driveway reduced to only 4m wide.
Proposed servicing arrangements Existing water, telecommunications and electrical
servicing from Seaview Tce.
New sewer and stormwater drainage connections will be
provided at building approval stage with existing
infrastructure within Seaview Tce. Any detention tanks
and pipes will be provided underground to ensure
stormwater impacts are non worsening in nature and
sewer pump complies with Unitywater standards.
Figure 4: Proposed development render
Page 9 of 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (planning report MCU19-0016.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.