Appendix D - traffic impact assessment
Attached to the e-mail MCU15/0111 & REC15/0031 Development Application D - Traffic Impact assessment Email 5 of 8.
Peak Hour Turn Movement Major Road Traffic
From Major Road Volume Parameter
2018 Base Year Without Development
QR = 39 vph max during AM Peak Hour QM = 1041 vpd total two-way AM Peak Hour
QR = 41 vph max during PM Peak Hour QM = 1076 vpd total two-way PM Peak Hour
QL = 3 vph max during AM Peak Hour QM = 752 vpd total two-way AM Peak Hour
QL = 3 vph max during PM Peak Hour QM = 546 vpd total two-way PM Peak Hour
2028 Design Horizon Year With Development
QR = 73 vph max during AM Peak Hour QM = 1507 vph total two-way AM Peak Hour
QR = 99 vph max during PM Peak Hour QM = 1559 vph total two-way PM Peak Hour
QL = 6 vph max during AM Peak Hour QM = 1086 vph total one-way AM Peak Hour
QL = 9 vph max during PM Peak Hour QM = 781 vph total one-way PM Peak Hour
Figure 3.2: Warrant for Turn Treatments at Elm Street / Pearsons Road Intersection
(Source: DTMR Roads Planning and Design Manual, Chapter 13, Figure 13.23)
This intersection was assessed using SIDRA software modelling. The key outcomes from this analysis are shown below
in Table 3-2.
B14158ER01 | TRAFFIC IMPACT ASSESSMENT | PALM LAKES RESORTS COOROY RETIREMENT COMMUNITY | 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.