20220728 Ltr Negotiated Decision Notice 17-19 Noosaville
Attached to the e-mail MCU21/0146 - Representations.
We conclude that Condition 5 of the Development Approval is not imposed for a proper planning
purpose, and unlawful and should be removed.
(2) Condition 14, which says
“Security in the Form of a cash bond or trading bank guarantee to the sum of $50,000 must be
submitted to Council, to secure performance of all conditions of this approval, prior to a pre-
start meeting. The cash bond or trading bank guarantee will be returned on performance of the
conditions of approval less any costs incurred by Council in respect of enforcing performance of
this permit. Council reserves the right to call upon the bond or guaranteed sum to effect
compliance with conditions”.
We conclude that Condition 14 is neither reasonable nor relevant as prescribed under the Planning
Act 2016 and should be removed. The condition is ambiguous in terms of release as conditions are
required to be maintained for the duration of the development.
(3) Condition 53, which says
“Prior to the prestart meeting, a bank guarantee or a bond of $30,000 must be lodged as security
for the protection of the tree/s identified for retention in the conditions of this approval. The
bond:
a) may be drawn upon by Council in its entirety if any one tree identified for retention
is damaged to the point where the tree cannot be saved (as confirmed by the
project arborist and agreed in writing by Council)
b) will be returned upon practical completion of all the operational works relating to
this development”.
We conclude that the condition is not reasonable and propose the following amendment:
“Prior to the prestart meeting, a bank guarantee or a bond of $30,000 must be lodged as security
for the protection of the tree/s identified for retention in the conditions of this approval. The
bond:
a) may be drawn upon by Council in its entirety if any one tree identified for retention
is damaged to the point where the tree cannot be saved (as confirmed by the
project arborist and agreed in writing by Council); and
b) the tree cannot be rehabilitated elsewhere on the site via new stock at a replanting ratio of
1:2 (in a location to be agreed to in writing by Council).
The bond will be returned upon practical completion of all the operational works relating to
this development (where a) and b) above are met)”.
Representations on Conditions of Approval
Stockwell’s representations and the facts and circumstances which support the representations are
outlined below:
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original