Appendix C - Engineering Plans

Attached to the e-mail Response to Council's Request for Information (REC17 /0011) - Email 01 of 01.

of 9

Page text shows just the words. Original shows the document exactly as it was published.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Haynes Consulting Engineers Pty Ltd
ABN No. 53613630078
P.O Box 549 Noosa Heads 4567

Ph: 0432 784 150




        27th June 2017                                                    File No:       1702


        Noosa Shire Council
        (by email)

        Attention:      Mark Lewis

        Dear Sir,

                      REC17/0011 – Eagle Rise Subdivision, Eagle Drive, Tewantin

        We are responding to engineering matters raised in your information request letter dated 21-
        4-17, and enclose IWMP Rev1 and plans 1702-01B, 1702-02A to 1702-07A inclusive.

        1 Consistent layout plans with Stormwater

        We enclose plan 1702-01B to show Murrays lot layout matching stormwater master plans.

        2 Turn area for subdivision stages

        We enclose plan 1702-07A with appropriate sealed turn areas for a garbage truck as per
        section 2.9 of PSP5. The concept is to have trucks entering one driveway in a forward
        direction and use verge when reversing. An easement over property is proposed to maintain
        access until adjacent subdivision is created and turn area is not required.

        3 Lot 7 access

        Access to lot 7 and 8 is via a concrete driveway that will be constructed as part of
        subdivision works in an access handle, refer to plan 1702-01B. Therefore no works in road
        reserve to north of lots 7 and 8 is required.

        4 Lot 12-16 Frontage work

        The existing verge at frontages of lots 12-18 is not far above existing top of kerb level. To
        obtain road flows to QUDM requirements the verge needs raising to 100mm above top of
        kerb level.

        As per plans 1702-01B and 1702-02A the works include:
            Footpath and verge re-shaping,
            Installation of stormwater pipe from subdivision to bio/detention basin,
            Adjustments to driveway levels at no 12, 16, 18 Eagle drive to obtain required height
               (design and permission to be obtained as part of Operational Works).

        5 Stormwater Management Plan

        Please note enclosed Integrated Water Management Plan Revision 1 (IWMP Rev 1),
        specifically Section 2.0 which responds to Information Request.



        C:\APROJECTS\1702 Eagle Drive\CORROUT\REC reply.docx
Log in to download the original file

Appendix C - Engineering Plans.pdf · 1.2 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.