Referecence Document Traffic Engineering Assessment Report 22 March 2023 131998.98121.5
Road Design and Construction Table 9.4.7.3 Criteria for assessable development (part)
Design Response
Performance outcomes Acceptable Outcomes
Road Design and Construction
PO10 AO10 Not Applicable
Roads and pathways are planned and Road planning and design is in There are no publicly available new roads
designed to support the function of the accordance with Council’s proposed as part of this Application.
road hierarchy and ensure that— Planning Scheme Policy PSP6
Engineering Design Standards – Internal roads have been tested by 12.5m
1. design and alignment of roads,
Roads, drainage and earthworks. and 14.5m buses and are fit-for-purpose.
intersections and all associated
works—
1. convey the primary function of
each type of street;
2. provide a safe environment for all
users;
3. are adequate for the design
speed environment;
4. are adequate for predicted traffic
volumes;
5. maintains the safe and efficient
functioning of the road network
incorporating roundabouts as a
preference to T intersections;
6. are compatible with existing
infrastructure;
7. are easily maintained by Council
equipment; and
8. where appropriate, have the
ability to accommodate public
transport services;
2. road pavement surfaces—
1. are durable enough to carry
estimated wheel loads of
travelling and parked vehicles;
2. provide for the safe passage of
vehicles, pedestrians, cyclists,
and discharge of stormwater run-
off from contributing catchments
and the preservation of all-
weather access;
3. kerb and channel—
www.bmctraffic.com.au 35
BMC22089: 59 Kabi Road, Cootharaba
22 March 2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.