Reference Document - Geotechnical Investigation Report - DBW24/0090 & RAP24/0025
Rebecca Stead 20248-001-Rev0
3 September 2020
the base of trenches/excavations/retaining walls/swimming pool, then rising up at 1V:1H, as illustrated in
Text Figure 10.
Text Figure 10: Footing depth required to prevent undermining
If any soil conditions encountered during construction are found to differ from those noted in the geotechnical
investigation, Tectonic should be notified immediately, and an inspection carried out to determine if changes
to footing design are required.
4.4 Retaining Walls
Retaining structures must be founded as per the recommendations in Section 4.3 above. Retaining
structures greater than 1 m high, or those required to support surcharge loads or sloping backfill, will require
engineer design and certification of construction. Retaining wall design should be carried out in accordance
with AS4678-2002 Earth retaining structures.
The parameters outlined in Table 3 may be adopted for retaining wall design. The values in Table 3 assume
that the walls are fully drained and no allowance is included for hydrostatic pressures, construction loading,
up-slope footing loadings, the effects of sloping ground and backfill compaction stresses. Any temporary
shoring required to support excavations during construction may also be designed using the parameters in
Table 3.
Table 1: Retaining Structure Design Parameters
Lateral earth pressure coefficients
Unit Friction
Retained material weight angle Ø
Ka Ko
(kN/m3) (°) Kp
(Cantilever wall) (Non-yielding wall)
Very Loose/ Loose
17 30 0.33 0.50 3.00
Sands
Medium Dense (or
18 34 0.28 0.44 3.54
Denser) Sands
Future Sand Fill(Note 1) 17 32 0.31 0.47 3.25
Note:
1) For sand fill placed and compacted as recommended in Section 4.2 above.
11/12
Document Set ID: 23080488
Version: 1, Version Date: 27/06/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Reference Document - Geotechnical Investigation Report - DBW24/0090 & RAP24/0025Related documentApplication case desk ↗
About this file
- File size
- 5.0 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.