NOOSA BOWLS CLUB REDEVELOPMENT – COLES GROUP
RESPONSE TO COUNCIL INFORMATION REQUEST FOR MCU
pipe can be buried reducing the extent of open drain in the park. Catchment A2 can
be discharged via a pipe drain onto the natural levels of the new road reserve
excised by Council from Pinaroo Park. Refer to revised IWMP by Aquaintel for
further details
2.3. Item 39
Information Required
In concurrence with landscape information request items, and concerns raised over
Stormwater Treatment Basin A, investigate ways to distribute the integrate water
quality improvement devices into areas of Carpark which will remain unaffected by
potential future development.
Response
Refer to response to item 38 above.
2.4. Item 40
Information Required
Investigate a revised detention design which does not require locating detention
tanks within road reserve to mitigate flows from private development.
Response
Refer response to item 37 above
2.5. \Item 44 & 45
Issue/Information Required
Propsed structures are located over/near the existing sewer main. Buildings or other
structures must provide at least 1.5 metres horizontal clearance from the outermost
projection of the structure to the nearest edge of any sewer infrastructure. Revise
drawings addressing the above comments. Additional drawing showing cross
sectional details of the proposed structures showing existing sewer.
Response
Sewer main has been relocated to avoid future building development. Bio filtration
basin C has been shifted to provide necessary clearance. Refer drawing 12691 –
SEW1.
Prepared by D Reynolds – RPEQ 9072
Tod Consulting – 13 August 2013
13 August 2013
Page 2 of 2
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.