2017-08-08 Planning & Environment Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 08 AUGUST 2017
Water Quality and Quantity
40. Except as otherwise modified herein, the development must be designed, constructed
and maintained to achieve the stormwater quality and quantity outcomes detailed in
the Site Based Stormwater Management Plan for 30-32 Doonella Street, Tewantin Rev
C by Bornhorst and Ward dated May 2017.
41. The development must include measures to prevent oils, hydrocarbons or other
pollutants likely to be released in basement areas from being released into Council’s
Stormwater system or other receiving waters.
42. Water quality treatment devices must be shaped and designed to be low maintenance,
and integrate into the landscape. Where bioretention devices are proposed, the
Operational Works Application for Stormwater Drainage, Landscaping and Earthworks
must demonstrate how the design is consistent with the most current version of the
Water by Design Bioretention Technical Design Guidelines.
43. Water Quality Treatment devices must be operated and maintained in accordance with
manufacturer’s specifications and relevant maintenance manuals.
44. Prior to commencement of use the Community Management Statement must include
provision for the engagement of personnel to operate and maintain Water Quality
Treatment devices in accordance with manufacturer’s specifications, relevant
maintenance manuals and the Site Based Stormwater Management Plan for 30-32
Doonella Street, Tewantin Rev C by Bornhorst and Ward dated May 2017.
Water Reuse
45. Detail design plans submitted with the Operational Works Application must
demonstrate how waters will be reticulated from the rainwater storage tank to reuse
areas with a minimum water use of 342KL per annum.
46. A suitable backflow prevention device must be installed on water reuse facilities to
protect the potable water within the reticulated water supply in accordance with
AS/NZS 3500:2003 Plumbing and Drainage.
WASTE MANAGEMENT
Waste Storage
47. The development must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy 9, Waste Management, including an external imperviously
paved area correctly sized for all refuse and recycling containers and suitably screened
from public places and neighbouring properties.
The waste management facilities should ensure recyclables bins are appropriately
sited and accessible, and/or provided with their own waste shute, to ensure recyclable
waste is not placed in the general waste shute.
48. The site must be provided with a bin wash area with a cold-water tap, hose and drain
outlet connected to sewer, via a bucket trap. The drain outlet is to be designed to
prevent storm water entry to the sewerage system which can be achieved by a bunded
area, with a nib wall height of 100mm maximum, enclosing a wash area of 700mm x
700mm minimum (max 0.7m²). Alternatively, the waste area can be roofed, or any
other appropriate design approved by Council.
Building Demolition/Removal/Relocation
49. A Waste Management Plan (construction and demolition) must be submitted and
approved by Council’s Environmental Health Officer prior to issue of a development
permit for operational works for demolition, removal or relocation of any building other
than a shed.
Page 44 of 84
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.