Appendix E - Stormwater Management Plan

Attached to the e-mail Multiple Housing – Type 3 Retirement & Special Needs (10 units) - MCU17/0551.

of 84

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (13.7 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
3.1.2     INFILTRATION LOSS & LAG PARAMETERS

Infiltration Loss and Lag Parameter values were adopted as per Water Technology’s Cooroy Flood Study (Report No.
J2835-01_R02v01 dated 26 July 2013), which covers the Cooroy region and site area. A parameter summary is provide
in Table 3-2 below.

                                 Table 3-2:   XP-RAFTS Calibration Parameter Summary

                    XP-RAFTS Model Parameter                       Value From Cooroy Flood Study

              Storage multiplication co-efficient Bx                                1

              Pervious Initial Rainfall Loss (mm)                                   10

              Pervious Continuing Rainfall Loss (mm/hr)                             2.5



Impervious Initial and Continuing Loss values were conservatively assumed as 0mm.

3.1.3     CHANNEL ROUTING

Channel Routing (XP-RAFTS Link Routing) was modelled as per Water Technology Cooroy Flood Study (2013). The ‘k’
lag values were determined directly based on flowpath length and average channel velocity of 0.9m/s for natural overland
flowpaths and 2.0m/s for runoff conveyed through drainage or road network. A constant ‘x’ coefficient of 0.2 was adopted
as per the Cooroy Flood Study (2013).

3.1.4     RAINFALL DATA

Rainfall data was generated based on rainfall IFD parameters provided by Water Technology’s Cooroy Flood Study
(Report No. J2835-01_R02v01 dated 26 July 2013) for the Cooroy Region.

3.1.5     EXISTING PEAKS FLOW

Modelling was undertaken for the all recurrence interval storm events up to and including the 100-year ARI storm event
with storm durations ranging from 30 to 120 minutes (these were considered the critical durations). Peak flow results for
the Existing Scenario have been provided in Table 3-3 below at the site discharge locations (i.e. Discharge Location A
and B as discussed in Section 2.3).

                                         Table 3-3:    Existing Peak Flow Results
                                        Peak Flow at Discharge         Peak Flow at Discharge
                           AEP
                                        Location A North (m3/s)       Location B Central (m3/s)
                           63%                   0.17                           1.14
                           39%                   0.26                           1.71
                           18%                   0.36                           2.54
                           10%                   0.43                           3.02
                           5%                    0.55                           3.69
                           2%                    0.66                           4.28
                           1%                    0.77                           4.95




16-001014-01B | STORMWATER MANAGEMENT PLAN                      COOROY RETIREMENT COMMUNITY, TRADING POST
(SWMP) | PALM LAKE RESORTS                                                                  ROAD, COOROY                    |8
Log in to download the original file

Appendix E - Stormwater Management Plan.pdf · 13.7 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.