RFI - Appendix G SWMP by MPN Consulting
16 December 2021
5.3.3.5 Water Quality Objectives
The Water Quality Objectives of the receiving waters for the proposed development have been
obtained from State Planning Policy July 2017. The State Planning Policy load reduction targets are
summarised in Table 3 below.
WATER QUALITY OBJECTIVES
Total Suspended Total Nitrogen Total Litter/Gross
Solids (TSS) % (TN) % Phosphorous Pollutants % Oils/Grease
Reduction Reduction (TP) % Reduction Reduction
No visible films
80 45 60 90
or odours
Table 3 – Water Quality Objectives
5.3.3.6 Treatment Plan
In order to achieve the Water Quality Objectives for the proposed development, it is proposed to
use natural treatment methods to treat the runoff prior to discharge from the site.
Stormwater runoff from the roof will be captured in a series of new gutters, downpipes and pits,
which will discharge along with the remaining on ground catchments to bioretention basins, where
Q1 flows will receive treatment while additional flows with discharge into the external stormwater
network.
Runoff from the existing landscape areas at the North and South East corner of the site will remain
generally as per pre-development conditions and will be treated by the existing grassed swale.
Approximately 260m2 of the access driveway and the carpark will bypass the bioretention basins.
This has been allowed for in the model so the overall net water quality objectives are achieved for
the development
Treated water will discharge off site via a proposed stormwater connection. The treatment plan for
the proposed development is depicted on MPN Plan 8293-CP.1.01 attached in Appendix 3, with
MUSIC excerpt below.
Excellence with Economy in Engineering 12
l:\paige work\8293\16-12-21 stormwater management plan_issue d.docx
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.