20240072 40 Cullinane St Combined

of 8

Page text shows just the words. Original shows the document exactly as it was published.

Original PDF page 2, section 1. The text section number identifies this passage in the reader.

     GENERAL NOTES                                                                            c. PARKING CONTROL SIGNS TO BE MOUNTED TO FACE APPROACHING TRAFFIC AT 45° TO
                                                                                                 KERB OR CARRIAGEWAY EDGE. ALL OTHER SIGNS TO BE TURNED AWAY BY 5° FROM THE            17. ADEQUATE SAFETY FENCING/BARRIERS TO BE APPLIED TO ALL BATTERS OR RETAINING
     1.   ALL DIMENSIONS SHOWN ARE IN METERS UNLESS OTHERWISE SHOWN.                             NORMAL TO APPROACHING HEADLIGHT.                                                          WALLS (TEMPORARY OR PERMANENT) AS PER RELEVANT AUSTRALIAN STANDARDS AND
                                                                                            3. SIGN SUPPORTS                                                                               LEGISLATION.
     2.   ALL SETOUT ON SITE IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR. CONTRACTOR         a. SLEEVED SIGNS SUPPORTS ARE TO BE PROVIDED IN ALL AREAS WHERE THEY ARE IN A
          TO ALLOW FOR ALL MEANS NECESSARY TO ACCURATELY SETOUT THE WORKS.                                                                                                             18. DUST CONTROL MEASURES ARE TO INCLUDE SPRAYING WATER ON UNPAVED ROADS,
                                                                                                 PAVED SURFACE.
                                                                                                                                                                                           ACCESS TRACKS AND STOCKPILES AT A SUFFICIENT LEVEL TO SUPPRESS DUST
                                                                                            4. LINEMARKING                                                                                 GENERATION. ADDITIONALLY CONTRACTORS ARE TO COVER OR ENCLOSE STOCKPILES
     3.   ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH PROJECT SPECIFICATIONS AND           a. REDUNDANT LINEMARKING IS TO BE GROUND OFF.
          WHERE FURTHER DETAILS ARE REQUIRED THE CONTRACTOR SHALL REFER TO MORETON                                                                                                         WHERE REASONABLY PRACTICAL TO RESTRICT DUST MOVEMENT.
                                                                                              b. THERMOPLASTIC LINEMARKING TO BE USED FOR ALL CONCRETE.
          BAY REGIONAL COUNCIL DEVELOPMENT GUIDELINES, LOCAL WATER AUTHORITY
          GUIDELINES, ASSOCIATED STANDARD DRAWINGS AND SPECIFICATIONS U.N.O.                                                                                                           19. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON THIS DRAWING, THE

     4.   SHOULD ANY OF THE CONSTRUCTED WORKS BE CONSTRUCTED OUTSIDE OF THE
                                                                                            JOINTING NOTES                                                                                 CONTRACTOR IS TO NOTIFY RECOR AND RECEIVE WRITTEN CONFIRMATION THAT WORKS
                                                                                                                                                                                           CAN COMMENCE.
          TOLERANCES SPECIFIED WITHIN THE PROJECT SPECIFICATION AND LOCAL AUTHORITY         1.     ALL JOINTING AND CONCRETE TO BE IN ACCORDANCE WITH THE REQUIREMENTS OF
          REQUIREMENTS, THE CONTRACTOR WILL RECTIFY AT THEIR COST INCLUSIVE OF ANY                 AS3727.1:2016.                                                                      20. ALL EXCAVATIONS ARE TO BE CONDUCTED IN ACCORDANCE WITH THE REQUIREMENTS OF
          ADDITIONAL COSTS INCURRED BY RECOR.                                               2.     SAW CUT JOINTS MUST BE:                                                                 THE GEOTECHNICAL ENGINEER AS OUTLINED IN THE GEOTECHNICAL INVESTIGATION
                                                                                                                                                                                           REPORT. TEMPORARY UNSURCHARGED CUTS IN LOOSE TO VERY LOOSE SAND TO BE
                                                                                                 a. BETWEEN 1 AND 1 OF CONCRETE PAVEMENT DEPTHS.                                           FORMED AT 1V:2H, AND IN MEDIUM DENSE SAND AT 1V:1H FOR BATTERS UP TO 3M IN
     5.   EXISTING SERVICES HAVE BEEN PLOTTED FROM SUPPLIED DATA AND AS SUCH THEIR                              4     3
          ACCURACY CANNOT BE GUARANTEED. NO RESPONSIBILITY IS TAKEN BY RECOR OR THE                                                                                                        HEIGHT. DEEPER CUTS ARE TO BE ASSESSED BY GEOTECHNICAL ENGINEER.
                                                                                              b. CLEARED OF ANY DEBRIS FROM THE CUTTING METHOD.
          PRINCIPAL FOR THE ACCURACY AND COMPLETENESS OF THIS INFORMATION. IT IS THE
          RESPONSIBILITY OF THE CONTRACTOR TO ACCURATELY ESTABLISH THE LOCATION AND           c. PERFORMED WITHIN 6 TO 12 HOURS OF FINISHING CONCRETE POURS.                           21. WHERE THE ABOVE TEMPORARY BATTER SLOPES CAN NOT BE ACHIEVED, TEMPORARY
          LEVEL OF ALL EXISTING SERVICES PRIOR THE COMMENCEMENT OF ANY WORKS. ANY           3. DOWELL BARS MUST BE INSTALLED EXACTLY 90° TO THE FACE OF JOINT TO ALLOW                     SHORING WILL BE REQUIRED UNDER THE ADVICE OF A SPECIALIST SHORING CONTRACTOR.
          DISCREPANCIES SHALL BE REPORTED TO THE SUPERINTENDENT. CONTRACTOR TO LOCATE            EXPANSION AND CONTRACTION MOVEMENTS.
          AND PROTECT SERVICES AS REQUIRED DURING PROPOSED WORKS.                           4. JOINTING LAYOUT TO BE CONFIRMED BY SUPERINTENDANT PRIOR TO CONSTRUCTION                 22. EXCAVATIONS IN PROXIMITY TO EXISTING STRUCTURES WILL REQUIRE SPECIFIC DESIGN
                                                                                                 COMMENCING. LAYOUT SHOULD AVOID ACUTE ANGLES IN THE CONCRETE SLAB AND AVOID               TO PREVENT UNDERMINING WHICH SHOULD BE CARRIED OUT BY A SUITABLY QUALIFIED
     6.   THE CONTRACTOR IS TO CHECK THROUGH LOCATING, POTHOLING AND SURVEY ALL                  MISMATCHED JOINTS.                                                                        AND EXPERIENCED RPEQ STRUCTURAL ENGINEER.
          CRITICAL CONNECTION POINTS FOR ALL CIVIL WORKS SHOWN ON THE DRAWINGS              5. JOINT SEALANTS WHERE USED MUST ADHERE TO SIDE OF JOINT FACES ONLY AND SHALL
          INCLUDING ANY POTENTIAL EXISTING SERVICES CLASHES PRIOR TO COMMENCEMENT OF             NOT EXTEND ABOVE SIDES OF JOINTS ONTO THE SLAB SURFACE.                               23. CONTRACTOR'S RPEQ GEOTECHNICAL ENGINEER IS TO CONFIRM THAT ANY CONSTRUCTED
          CIVIL WORKS. CONTRACTOR TO IMMEDIATELY REPORT ANY DISCREPANCIES TO RECOR          6. DOWEL BARS ARE TO BE                                                                        CUT/FILL BATTERS AND RETAINING STRUCTURES ON THE SITE HAVE ACHIEVED ADEQUATE
          AND AWAIT FORMAL DIRECTION PRIOR TO COMMENCING CIVIL WORKS.                         a. FOR 100MM THICK SLAB, 12MM Ø OF LENGTH 300MM AND SPACED AT 400MM CENTRES                  STABILITY WITH A LONG-TERM FACTOR OF SAFETY AGAINST GEOTECHNICAL FAILURES TO
                                                                                              b. FOR 125MM THICK SLAB, 16MM Ø OF LENGTH 350MM AND SPACED AT 300MM CENTRES                  THEIR SATISFACTION.
     7.   ON COMPLETION OF SERVICES INSTALLATION, ALL DISTURBED AREAS SHALL BE RESTORED       c. FOR 150MM THICK SLAB, 20MM Ø OF LENGTH 400MM AND SPACED AT 300MM CENTRES
          TO ORIGINAL LEVEL, INCLUDING KERBS, FOOTPATHS, CONCRETE AREAS, GRAVEL AREAS,                                                                                                 24. EARTHWORKS LEVELS SHOWN ARE FINISHED SURFACE LEVELS INCLUSIVE OF TOPSOIL
          GRASSED AREAS AND ROAD PAVEMENTS.                                                                                                                                                LAYER. REFER TO STRUCTURAL ENGINEERING DRAWINGS FOR BUILDING SLAB

     8.   CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIR OF ANY DAMAGE TO
                                                                                            EARTHWORKS NOTES                                                                               THICKNESSES AND HYDRAULIC DRAWINGS FOR SUB-FLOOR DRAINAGE FOR
                                                                                                                                                                                           DETERMINATION OF REQUIRED BULK EARTHWORKS SURFACE.
          AUTHORITY/COUNCIL'S INFRASTRUCTURE. SUCH REPAIR OR REINSTATEMENT TO BE            1.     FOR DETAILED GEOTECHNICAL INFORMATION, REFER GEOTECHNICAL INVESTIGATION
          CARRIED OUT IMMEDIATELY TO THE SATISFACTION OF INFRASTRUCTURE                            REPORT BY GEOTECHNICAL ENGINEER. IT IS RECOMMENDED THAT THE GEOTECHNICAL            25. ANY PRELOADING REQUIRED IS TO OCCUR IN ACCORDANCE WITH THE GEOTECHNICAL
          OWNER/MANAGER / AUTHORITY/COUNCIL.                                                       CONSULTANT BE CONTACTED TO CONFIRM THE SOIL CONDITIONS PRIOR TO EARTHWORKS              ENGINEERS REQUIREMENTS. CONTRACTOR TO ALLOW FOR THE IMPORT AND REMOVAL OF
                                                                                                   COMMENCING.                                                                             ALL NECESSARY MATERIAL TO UNDERTAKE THE PRELOADING OPERATIONS.
     9.   CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH ALL WORKPLACE HEALTH
          AND SAFETY REQUIREMENTS.                                                          2.     GRASS AND TOPSOIL SHALL BE STRIPPED TO A MINIMUM DEPTH OF 100MM OVER THE            26. REFER ARCHITECTURAL DRAWINGS FOR BUILDING SETOUT.
                                                                                                   EXTENT OF THE WORKS UNLESS DIRECTED OTHERWISE AND STOCKPILED WHERE
     10. WHERE ANY EXCAVATION OR CONSTRUCTION WORKS ARE TO BE IN CLOSE PROXIMITY TO                REQUIRED FOR FILL OF LANDSCAPING AREAS. TOPSOIL MATERIALS MUST NOT BE USED IN
         NEIGHBOURING LOT BOUNDARIES OR INFRASTRUCTURE, CONTRACTOR TO ALLOW IN
         SCOPE OF WORKS TO PROVIDE ALL MEASURES NECESSARY TO ENSURE THE INTEGRITY OF        3.
                                                                                                   STRUCTURAL FILL.
                                                                                                   UNSUITABLE NATURAL MATERIALS SUCH AS SATURATED, LOOSE OR SOFT MATERIALS            INSPECTIONS
         EXISTING BOUNDARIES AND INFRASTRUCTURE. THIS MAY INCLUDE THE USE OF LOW                   ENCOUNTERED SHOULD BE REMOVED DURING SUBGRADE PREPARATION FOR BULK
                                                                                                                                                                                       THE FOLLOWING INSPECTIONS MUST BE COMPLETED BY RECOR ENGINEERS BEFORE
         VIBRATION EQUIPMENT, TRENCH SHORING ETC AS REQUIRED.                                      EARTHWORKS. ALL UNSUITABLE MATERIAL TO BE REMOVED FROM SITE AT CONTRACTORS
                                                                                                                                                                                       ENGINEERING CERTIFICATION WILL BE ISSUED. THE CONTRACTOR IS TO PROVIDE A MINIMUM OF
                                                                                                   EXPENSE.
                                                                                                                                                                                       72 HOURS NOTICE TO RECOR FOR REQUIRED INSPECTIONS. SHOULD THE CONTRACTOR FAIL TO
     11. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON THESE DRAWINGS,                                                                                                      REQUEST AN INSPECTION, THE CONTRACTOR WILL BE RESPONSIBLE FOR ALL COSTS TO ALLOW
         THE CONTRACTOR IS TO NOTIFY RECOR AND RECEIVE WRITTEN CONFIRMATION THAT            4.     COMPACTION OF THE EXPOSED SAND SUBGRADE REQUIRES SUBSTANTIAL VOLUMES OF             FOR THE WORKS TO BE INSPECTED TO THE SATISFACTION OF RECOR. ANY INSPECTIONS THAT
         WORKS CAN COMMENCE.                                                                       WATER COMBINED WITH VIBRATORY COMPACTION EQUIPMENT. CARE MUST BE TAKEN TO           FAIL ARE TO BE RE-INSPECTED WITH ALL REINSPECTION COSTS TO BE PAID BY THE
                                                                                                   ENSURE THERE ARE NO IMPACTS ON SURROUNDING STRUCTURES. MATERIAL TO BE               CONTRACTOR.
     12. CONTRACTOR TO PROVIDE AS CONSTRUCTED DRAWINGS FOR ALL CONSTRUCTED WORKS                   COMPACTED IN ACCORDANCE WITH GEOTECHNICAL REPORT AND AS1289.
         IN ACCORDANCE WITH LOCAL GOVERNMENT REQUIREMENTS. UNLESS OTHERWISE                                                                                                              a. PRESTART
         ADVISED BY RECOR CONTRACTOR TO NOTE COUNCILS ADAC REQUIREMENTS.                    5.     A MINIMUM 150MM THICK GRANULAR WORKING PLATFORM MAY BE REQUIRED ON SOIL
                                                                                                   SUBGRADES ALONG HAUL ROADS AND LAYDOWN AREAS TO IMPROVE TRAFFICABILITY.
                                                                                                                                                                                         b. EARTHWORKS - FINAL STRIPPING OF TOPSOIL, INSTALLATION OF SEDIMENT AND EROSION
     13. CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH RELEVANT APPROVALS.                  SPECIFIC PLATFORM DESIGN WOULD BE REQUIRED PRIOR TO MOBILISATION AND
                                                                                                   TRAFFICKING OF ANY HEAVY MOBILE PLANT ON THE SITE.                                       CONTROL MEASURES UNSUITABLE GROUND
     14. CONTRACTOR TO ALLOW TO LIASE/CO-ORDINATE WITH ELECTRICAL, LANDSCAPE AND
         OTHER SERVICE CONTRACTORS THROUGHOUT CIVIL CONSTRUCTION.                           6.     IMPORTED GENERAL FILL MATERIAL SHALL BE SUPPLIED AND COMPACTED WHERE                  c. SIDE AND CUT OFF DRAINS
                                                                                                   UNSUITABLE NATURAL MATERIALS ARE LOCATED AND AS OTHERWISE NECESSARY TO
     15. CONTRACTOR TO ORGANISE ALL DEMOLITION PERMITS PRIOR DEMOLITION WORKS                      OBTAIN SUBGRADE/PLATFORM LEVEL. IMPORTED GENERAL FILL MATERIAL SHALL BE CLEAN         d. STORMWATER PIPE LAID ON BEDDING PRIOR TO BACKFILL
         COMMENCING ON SITE.                                                                       GRADED MATERIAL FREE OF ORGANIC MATTER AND STONES, WITH MAXIMUM PARTICLE
                                                                                                   SIZE OF 100MM AND CAPABLE OF BEING COMPACTED INTO COHERENT FILLING TO THE
                                                                                                   SPECIFIED STANDARD. THE MATERIAL SHALL HAVE A MAXIMUM PLASTICITY INDEX OF 15%, A      e. STORMWATER TRENCH BACKFILLED PRIOR TO PAVEMENT PLACEMENT
     16. CONTRACTOR TO ALLOW TO DEMOLISH ALL EXISTING STRUCTURES, ROADS AND SERVICES
                                                                                                   SHRINK-SWELL INDEX OF LESS THAN OR EQUAL TO 1% AND A MINIMUM C.B.R. OF 10%.
         WITHIN LIMIT OF WORKS AND REMOVE FROM SITE U.N.O.
                                                                                                                                                                                         f. STORMWATER STRUCTURE BASE SLABS
                                                                                            7.     ALL EARTHWORKS TO BE CARRIED OUT AT +/- 2% OPTIMUM MOISTURE CONTENT FOR
     17. CONTRACTOR TO UNDERTAKE DILAPIDATION REPORT FOR ADJOINING PROPERTIES AND
                                                                                                   STANDARD COMPACTION.                                                                  g. PAVEMENT SUBGRADE
         COUNCIL ROADS AND VERGES PRIOR TO COMMENCEMENT OF ANY WORKS ON SITE.

                                                                                            8.     ANY PROPOSED RETAINING WALL WORKS MUST BE WHOLLY WITHIN THE PROPERTY                  h. PAVEMENT REINFORCING
     18. CONTRACTOR TO CLEAR AND GRUB ALL VEGETATION ON SITE AS IDENTIFIED IN THE
                                                                                                   BOUNDARY OF THE SUBJECT SITE, INCLUDING REAR OF RETAINING WALL DRAINAGE
         APPROVED VEGETATION MANAGEMENT PLAN. CONTRACTOR TO ENSURE ALL TREE ROOTS
                                                                                                   INFRASTRUCTURE FOR RETAINING WALLS IN CUT. RETAINING WALLS ARE TO BE PREPARED
         AND STUMPS ARE COMPLETELY REMOVED AND BACKFILLED TO LEVEL 1 SUPERVISION.                                                                                                        i. PAVEMENT PRIOR TO SEALING (PRESEAL)
                                                                                                   IN ACCORDANCE WITH STRUCTURAL ENGINEERS SPECIFICATIONS, AND IN CONFORMANCE
         CONTRACTOR TO ALLOW TO MULCH ALL CLEARED VEGETATION AND STOCKPILE ON SITE
                                                                                                   WITH CONSTRUCTION REQUIREMENTS OF GEOTECHNICAL REPORT.
         OR REMOVE FROM SITE AS DIRECTED.
     19. DRAWINGS TO BE READ IN CONJUNCTION WITH ARCHITECT, SURVEYOR, HYDRAULICS, ETC.                                                                                                   j. RETAINING WALL FOOTING REINFORCING
         CONSULTANT AND CONTRACTOR DRAWINGS.                                                9.     REFER ARCHITECT/LANDSCAPE ARCHITECT DRAWINGS FOR CONFIRMATION OF RETAINING
                                                                                                   WALL COLOUR AND FINISH.                                                               k. RETAINING WALL BLOCKWORK PRIOR TO CORE FILL
     20. CONTRACTOR TO PREPARE AND HAVE APPROVED BY RELEVANT AUTHORITY: ROAD
         OPENING PERMIT AND TRAFFIC MANAGEMENT PLAN FOR ALL WORKS WITHIN COUNCIL            10. ALL EARTHWORKS OPERATIONS SHALL BE CARRIED OUT WITH 'LEVEL 2' SOIL ENGINEERING
                                                                                                                                                                                         l. STEEL REINFORCEMENT OF CONCRETE STRUCTURES
         ROAD RESERVES. CONTRACTOR TO ALLOW FOR ALL COSTS ASSOCIATED WITH                       SUPERVISION IN ACCORDANCE WITH APPENDIX B OF AS 3798. THE NOMINATED
         IMPLEMENTATION OF THE TMP.                                                             GEOTECHNICAL TESTING AUTHORITY SHALL PROVIDE CERTIFICATION THAT ALL GENERAL
                                                                                                EARTHWORKS OPERATIONS HAVE BEEN CARRIED OUT IN ACCORDANCE WITH THE                       m. PRACTICAL COMPLETION
                                                                                                DRAWINGS AND SPECIFICATIONS AND THE CONTROLLED FILL IS SUITABLE FOR PURPOSE
     21. ALL WORKS TO BE COMPLETED IN ACCORDANCE WITH ALL LOCAL AUTHORITY APPROVALS
                                                                                                TO THE REQUIRED BEARING CAPACITY UNDER THE PLATFORM/STRUCTURES AS SPECIFIED              n. ON MAINTENANCE
         RECEIVED FOR THE PROJECT AND IN ACCORDANCE WITH OPW APPROVALS BY COUNCIL.
                                                                                                BY THE GEOTECHNICAL REPORT.
     22. NO WORKS ARE TO BE UNDERTAKEN ON LAND OUTSIDE OF THE SITE BOUNDARY WITHOUT                                                                                                      o. OFF MAINTENANCE
                                                                                            11. ALL EARTHWORKS FILL AND EXCAVATED AREAS SHALL BE COMPACTED TO 98% STANDARD
         FORMAL APPROVAL BY THE OWNER/CUSTODIAN OF THAT LAND INCLUDING BUT NOT
                                                                                                MAXIMUM DRY DENSITY OR A DRY DENSITY INDEX OF AT LEAST 75% IN ACCORDANCE WITH
         LIMITED TO PRIVATE PROPERTY, ROAD RESERVE, PARKS/OPENSPACE, EASEMENTS.
                                                                                                THE GEOTECHNICAL REPORT IN LAYERS OF 250MM LOOSE THICKNESS (PRIOR TO                     p. ANY OTHER INSPECTION AS SPECIFIED BY LOCAL COUNCIL (REFER DEVELOPMENT
                                                                                                COMPACTION).                                                                                APPROVAL)
     23. THE CONTRACTOR SHALL HAVE AN APPROVED SET OF CONSTRUCTION DRAWINGS AND
         APPROVALS ON SITE AT ALL TIMES.
                                                                                            12. COMPACTION TESTING TO BE CARRIED OUT AT A MINIMUM OF TWO TESTS PER VERTICAL
                                                                                                LIFT WHERE STRUCTURAL FILL HEIGHTS EXCEED 300MM IN ACCORDANCE WITH AS3798.
     24. ALL WATER AND SEWER RETICULATION WORKS TO BE CONSTRUCTED IN ACCORDANCE                 CONTRACTOR TO UNDERTAKE ALL EARTHWORKS TESTING IN ACCORDANCE WITH
         WITH THE UNITYWATER SUPPLY AND SEWERAGE DESIGN AND CONSTRUCTION CODE (2013).           GEOTECHNICAL ENGINEER AND LOCAL AUTHORITY REQUIREMENTS.

     STANDARD SIGNS AND LINE MARKING NOTES                                                  13. FINISHED SURFACES TO ALL DISTURBED AREAS ARE TO BE TREATED IN ACCORDANCE WITH
                                                                                                LANDSCAPE DRAWINGS.
     1.   GENERAL
       a. ALL SIGNS AND PAVEMENT MARKING IS TO BE IN ACCORDANCE WITH THE QUEENSLAND         14. ALL NEW WORKS TO MATCH NEATLY INTO EXISTING LEVELS.
          TRANSPORT MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES (CURRENT EDITION).
     2. SIGNS                                                                               15. ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH APPROVED MANAGEMENT PLANS.
       a. ALL SIGNS TO BE REFLECTORISED CLASS 1 TO AS1906.1:2007 UNLESS NOTED OTHERWISE.
       b. SIGNS ARE TO BE INSTALLED WITH THE FOLLOWING CLEARANCES TO EDGE OF SIGN:          16. CONTRACTOR TO ENSURE SUITABLE EROSION CONTROL MEASURES ARE INSTALLED
          LOCATION CLEARANCE NO KERB 600 BEHIND GUIDE POSTS BARRIER KERB 300 FROM FACE          INCLUDING BUT NOT LIMITED TO SHAKE DOWNS, SILT FENCE ETC IN ACCORDANCE WITH
          MOUNTABLE KERB 500 FROM FACE OF KERB.                                                 EROSION AND SEDIMENT CONTROL PLAN




                                                                                                  North Point       Approved                                                                                                                                                                                               Project Address                 Title

                                                                                                                                                                                                                                                                                                                           40 CULLINANE STREET, TEWANTIN   GENERAL NOTES
                                                                                                                            ADAM BROUGHTON RPEQ 8915

                                                                                                                    For and on behalf of RECOR Pty Ltd.
                                                                                                                    Scale                                                                                                ENGINEERING & PROJECT SERVICES                                                                    Client Details                  Project Name                            Sheet Size
                                                                                                                                                                                                                            SUNSHINE COAST | BRISBANE
 B        23.07.24   RFI AMENDMENTS                                           AB       MP                                                                 NTS                                                              www.recor.au | ABN 89 647 469 707                                                               WALT CONSTRUCTION               40 CULLINANE STREET, TEWANTIN              A1
 A        08.05.24   ISSUE FOR APPROVAL                                       AB       MP                                                                                             COPYRIGHT © This drawing is subject to copyright in accordance with the agreement between RECOR Pty Ltd and RECOR's                                                  Project Number         Drawing Number    Revision

                                                                                                                                                                                                                                                                                                                                                           20240072               C005                B
                                                                                                                                                                                      client. This drawing shall only be used for this specific project. This drawing shall not be used for construction until marked as

Rev       Date                    Revision Description                     Drawn Check                                                   DO NOT SCALE, IF IN DOUBT ASK                                                      'Issued For Construction' in the revision description.
Log in to download the original file

20240072 40 Cullinane St Combined.pdf · 6.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.