Original source · versioned page text
Ltr-20190925-IR Response-Noosa Marketplace_FINAL (1)
Figure 36 – Waste management locations
Picture 23 – Waste storage locations
Source: MRA
ISSUE 7: TRAFFIC LAYOUT DETAILS
A full response and additional detail with accompanying cover letter is provided by Cambray
Consulting and included in Appendix F. The following summarises and contextualises the response
to sub-items 23 to 34.
Further traffic layout details are required to assess the proposal.
Information Required
23. Demonstrate how the one-way operation of the main loading area will be satisfactorily
managed, including signage where necessary.
Response to sub-item 23:
The one-way operation of the main loading area will be satisfactory managed through the use of
suitable line marking and signage provisions throughout the main loading area. An updated swept
path and servicing assessment have been prepared and included in the revised Traffic Impact
Assessment Report in Appendix F for more details. Signage will be provided to the loading dock
movement. The proposed signages will be provided in accordance with the requirements of MUTCD
and will be resolved during the post approval stage.
Ltr-20190925-IR Response-Noosa Marketplace_FINAL 58
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.