7. Earthworks Code
Performance outcomes Acceptable Outcomes
Local amenity
PO4 AO4.1 Complies
Undertaking earthworks does not adversely impact The following control measures are implemented— Regular watering will be undertaken as required
on the amenity of the local area by way of dust, during the construction phase to minimise any dust
noise or visual amenity. 1. regular water spraying of exposed emissions. An ESC plan has been prepared for the
areas to suppress dust; construction phase as part of the Engineer report
2. provision of dust stabilised or sealed and plans. (Refer to Appendix E).
internal roads;
3. protective covering of exposed areas All disturbed areas will be stablished, should they
that are left for more than 2 weeks; be exposed for periods exceeding 2 weeks.
and
4. unless a development permit provides
otherwise, disturbed areas are
revegetated using species identified in
Council's Planning Scheme
Policy PSP2 Landscaping.
AO4.2 Complies
Earthworks are undertaken only during the hours of Filling and earthworks will only be undertaken
7:00am to 6:00pm, Monday to Friday and 7:00am to between the hours nominated in AO4.2.
3:00pm on Saturday. No work is undertaken on
Sunday or public holidays.