2.4 Standard Specifications and Drawings

The Contractor shall maintain on site all relevant standard specifications and drawings issued by the
SCRC.

2.5 Prestart Meeting

Seven (7) days notice shall be given prior to commencement of construction. The following people are
required on site for a Prestart Meeting:

» Contractor's Engineer/Project Manager;
» Contractor's Site Supervisor;
» Project Superintendent;

» Council's Engineer/Inspector

2.6 Inspections by the Sunshine Coast Regional Council (SCRC)

Officers of the SCRC may make random inspections of the works at any time. The Contractor shall co-
operate fully with Council Officers making inspections.

Specific approvals from the SCRC that will be required include:

Roadworks and Drainage

» Pavement design approval, based on soaked CBR tests arranged by the Contractor;

» Subgrade inspection, after boxing out but prior to installation of the side drains;

» Pre-seal inspection, after placement pavement before the pavement is primed;

» On-maintenance inspection, after works are completed;

» Off-maintenance inspection, at the end of Council's twelve-month maintenance period;

At least 48 hours prior to the time when the works will be ready for testing or inspection in relation to any
of the tests required by Council, the Contractor shall contact the Superintendent to arrange a mutually
acceptable time for such testing or inspection to be carried out.

The Contractor shall allow for all necessary inspection, testing and approvals in the works programme
and no extension of time will be granted for delays so resulting.

If reinspection is required where the works are not approved or a test fails, the Contractor shall be
responsible for any re-inspection fees or charges that may be charged by the Council.

2.7 On-Maintenance Inspection

Prior to Council inspection, the Contractor shall arrange for all roads to be cleaned, gutters swept,
footpaths reinstated and all drainage systems to be flushed and cleaned and costs shall be included in
the Tender Lump Sum.

41/22382/11840 Girraween Sports Precinct 13
Earthworks Package

Used in these records

About this file

File size
20.7 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

06_1168 - Change a Development Approval [As Published].pdf · 20.7 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.