12. Noise Management

12.1 General

A number of the activities associated with construction on the site will generate noise. These may include
use of heavy machinery for earthworks, operation of cranes and heavy vehicles accessing the site to
deliver construction materials.

12.2 Objectives

» To comply with relevant environmental legislation (e.g. Environmental Protection Act 1994 and the
associated EPP (Noise)).

» All construction works shall be undertaken in such a way so as to minimise noise impacts and
potential for nuisance to be caused to surrounding sensitive receivers (including sensitive fauna
habitat).

12.3 Requirements

12.3.1. Hours of Operation

» The hours of operation at the construction site shall be Monday — Saturday 6.30am — 6.00pm, with
activities likely to generate significant noise levels limited to times least likely to impose noise
disturbance.

» Noconstruction or earthworks activities including movement of trucks and heavy machinery are to be
conducted on Sundays or any public holidays.

12.3.2. General Construction Site Conditions

» Heavy vehicles accessing either project site will comply with local speed limits when travelling along
local street networks. Further, heavy vehicles will be restricted to low speeds (10 km/hr) upon access
to the construction site

» Where available, consideration should be given to employing plant and machinery on-site which
include noise suppressors or are equipped with electric motors as opposed to diesel operated motors.

» Complaints relating to noise annoyance are to be received by the Construction Manager and duly
recorded. An example complaints form has been included in Appendix C of this document.

12.4 Responsibilities

12.4.1 Construction Manager
The Construction Manager will be responsible for the following:

» In conjunction with the Site Foreman, enforcing all of the above requirements which also apply to all
sub-contractors working on-site throughout the construction phase.

41/22382/12186 Girraween Sports Precinct 7
Environmental Management Plan (Construction)

Used in these records

About this file

File size
20.7 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

06_1168 - Change a Development Approval [As Published].pdf · 20.7 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.