Referral Agency Response - Planning RAP24 0038 (As Published) · DBW24/0122

of 5

Text shows just the words. Original shows the document exactly as it was published.

                                                                            Officer:            Tiani Bird
                                                                            Direct Telephone:   07 5329 6389
                                                                            Our Reference:      RAP24/0038 & DBW24/0122
                                                                            Your Reference:     2024-72

                 16 April 2025


                 CE Carey & MBR Carey
                 C/- Danya Cook Town Planning
                 PO Box 9410
                 PACIFIC PARADISE QLD 4564

                 [email protected]



                 Dear Sir/Madam,
                                                  Referral Agency Response
                                                        Planning Act 2016

                 I refer to your application and advise that Council, as a referral agency for the application,
                 completed its assessment of the application on 10 April 2025. You are advised that Council
                 requires conditions to be attached to any development approval. The conditions are listed
                 below.
                 1.      APPLICATION DETAILS

                     Application No:               RAP24/0038

                     Street address:               7 Masthead Quay, Noosaville Qld 4566

                     Real property description:    Lot 593 RP 883861

                     Planning Scheme:              Noosa Plan 2020 (25 September 2020)

                 2.      TYPE OF DEVELOPMENT

                 The applicant seeks the following type of referral agency response:
                 •       Referral Agency Response for a Dwelling House (Setbacks & Structures within 4.5m of
                         Revetment Wall
                 3.      REFERRAL AGENCY CONDITIONS

                         When Conditions must be Complied With
                 1.      Unless otherwise stated, all conditions of this Decision Notice must be complied with
                         prior to the use of the extensions commencing, and then compliance maintained at all
                         times while the use continues.
                         Approved Plans
                 2.      Development authorised by this approval must be undertaken generally in accordance
                         with the Approved Plans listed in the tables below.



                 ABN 97.969.214.121                                                                    PO Box 141
                 noosa.qld.gov.au                                                               Tewantin QLD 4565
                 [email protected]                                                               07 5329 6500
                                                                                                           Page 1 of 5
Document Set ID: 23690367
Version: 4, Version Date: 16/04/2025
Log in to download the original file

Referral Agency Response - Planning RAP24 0038 (As Published).pdf · 133 KB (small file)

Full text of the other 4 pages

Page 2

                           Plan No.            Rev.   Plan/Document Name                         Date

                           WD.2.01             I      Site Plan, prepared by Garland Design      27/02/2025
                                                      Annotated by Council

                           WD.2.03A            I      Ground Floor Plan, prepared by Garland 27/02/2025
                                                      Design

                           WD.2.04             I      Level 1 Floor Plan, prepared by Garland 27/02/2025
                                                      Design

                           WD.2.07             I      Roof Plan, prepared by Garland Design      27/02/2025

                           WD.3.01             I      Elevations, prepared by Garland Design     27/02/2025

                           WD.3.02             I      Elevations, prepared by Garland Design     27/02/2025

                        Building Height
                 3.     The maximum height of the development must not exceed 8 metres above the ground
                        level.
                 4.     Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld)
                        which certifies that the building does not exceed the maximum height requirement of this
                        Decision Notice.
                        Noosa Waters Setback
                 5.     The area within 4.5 metres of the centre line of the top of the concrete revetment wall
                        must be developed in accordance with the following:
                        (a)     A minimum of 25% of the area must be planted with shrubs and small trees with a
                                mature height of 3m or less.
                        (b)     A maximum of 25% of the area may be impervious, with the balance area soft
                                landscaping (i.e. grass, ground covers, shrubs and small trees).
                        (c)     The ground surface within 1 metre of the revetment wall must be grass or ground
                                cover and must not include shrubs or hard pavement.
                        (d)     Any side boundary fencing must taper down to a maximum height of 1.2 metres at
                                the revetment wall and have a height not exceeding 1.5 metres at a distance of
                                2.25 metres from the revetment wall.
                        (e)     Any retaining structures, planter boxes or the like must be finished with natural
                                materials such as timber or rock rather than manufactured materials.
                 6.     No shore side anchor points are permitted within 4.5m of the revetment wall.
                        Bonds
                 7.     A site compliance bond of $5,000 is to be submitted to Council prior to the
                        commencement of works. The commencement of works can only commence once
                        Council's Construction Engineering Officer has confirmation that the bond monies have
                        been received by Council.
                        The bond will be refunded less any costs incurred by Council in ensuring compliance
                        with these conditions or any additional inspections incurred for substandard work or work
                        undertaken not in accordance with this permit.




                                                                                                         Page 2 of 5
Document Set ID: 23690367
Version: 4, Version Date: 16/04/2025

Page 3

                 8.     Bonds must:
                        (a)     Meet the requirements of council’s relevant Planning Scheme Policy for
                                performance and uncompleted works;
                        (b)     Be lodged with Council and accompanied by the Bond Administration Fee/s; and
                        (c)     Be requested for release by writing to Council, when relevant approval
                                requirements have been met.
                        Earthworks
                 9.     All earthworks and associated retaining structures/batters must be contained entirely
                        within the subject site unless written permission from the respective landowner(s) is
                        provided to Council. All earthworks must be undertaken in accordance with the
                        provisions of Australian Standard AS3798: Guidelines on Earthworks for Commercial
                        and Residential Developments.
                 10.    Earthworks carried out on site must not affect the structural integrity of the revetment
                        wall, existing fences or other structures that border the subject site. Fences that are
                        affected must be replaced in a timely manner and in consultation and agreement of the
                        owners of the related properties.
                        Revetment Wall / Flood Storage
                 11.    All works within the 4.5m setback from the revetment wall must be carried out generally
                        in accordance with Linday Consulting’s Flood Storage Model Site Plan (24-1071-F1,
                        Rev. A) and Flood Storage Model Perspective Model (24-1071-F2, Rev. A) dated 29
                        December 2024.
                 12.    All works for the purpose of increasing available flood storage must be located within
                        the 4.5m setback from the revetment wall.
                 13.    Certification of the completed works within the 4.5m setback from the revetment wall
                        must be submitted to Council within 3 months of the completion of the works. The
                        certification must be prepared by a RPEQ (Registered Professional Engineer of
                        Queensland) and state that the works:
                        (a)     Have not reduced the amount of available flood storage within the 4.5m setback
                                from the revetment wall;
                        (b)     Have not negatively impacted the stability of the revetment wall or negatively
                                impacted the associated membrane;
                        (c)     Have not reduced the available flood storage within the lot from the profile as
                                described in The Noosa Plan 2020 – Low Density Residential Zone Code; and
                        (d)     Meet the relevant conditions of this approval.
                 4.     REASONS FOR REFERRAL AGENCY’S DECISION

                 The proposal is subject to specific built form parameters outlined in Noosa Plan 2020.
                 5.     TIME LIMIT FOR MAKING FURTHER APPLICATION

                 Pursuant to section 54(4) of the Planning Act 2016, you will not be required to refer your
                 building works application to council for a further Referral Agency Response if:
                 (a)    you submit this Referral Agency Response in its entirety, including all referenced plans
                        and documents, when making the application to the Assessment Manager; and
                 (b)    there are no changes to the proposal that was presented to council with this referral;
                        and




                                                                                                         Page 3 of 5
Document Set ID: 23690367
Version: 4, Version Date: 16/04/2025

Page 4

                 (c)    The development application to the assessment manager is made within 12 months of
                        the date of this referral agency response.
                 6.     ADVISORY NOTES

                 The following notes are included for guidance and information purposes only and do not form
                 part of the referral agency conditions:
                        Aboriginal Cultural Heritage Act 2003
                 1.     There may be a requirement to establish a Cultural Heritage Management Plan and/or
                        obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
                        The ACH Act establishes a cultural heritage duty of care which provides that: “A person
                        who carries out an activity must take all reasonable and practicable measures to ensure
                        the activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply
                        with the duty of care. Substantial monetary penalties may apply to individuals or
                        corporations breaching this duty of care. Injunctions may also be issued by the Land
                        and Resources Tribunal, and the Minister administering the ACH Act can also issue stop
                        orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
                        the cultural heritage value of Aboriginal cultural heritage.
                        You should contact the Cultural Heritage Unit to discuss any obligations under the ACH
                        Act.
                        Equitable Access and Facilities
                 2.     The plans for the proposed building work have NOT been assessed for compliance with
                        the requirements of the National Construction Code - Building Code of Australia (Volume
                        1) as they relate to people with disabilities. Your attention is also directed to the fact
                        that in addition to the requirements of the National Construction Code as they relate to
                        people with disabilities, one or more of the following may impact on the proposed
                        building work:
                        (a)     the Disability Discrimination Act 1992 (Commonwealth);
                        (b)     the Anti-Discrimination Act 1991 (Queensland); and
                        (c)     the Disability (Access to Premises – Buildings) Standards.
                        Fires in Urban Areas
                 3.     In urban areas fires are prohibited except where in an appliance is used for domestic
                        heating or cooking purposes, which must comply with particular standards. Any area
                        identified as a fire pit area on approved plans is to be in accordance with Local Law &
                        Subordinate Local Law No. 3, Schedule 3. Refer to the following link for details:
                        https://www.noosa.qld.gov.au/community/local-laws/local-laws-overview
                        Infrastructure Charges
                 4.     All developments and/or changes to existing developments may require payment of
                        “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges
                        Resolution” made pursuant to the planning legislation and regulations current at the time
                        of issue. For further information, please refer to https://www.noosa.qld.gov.au/planning-
                        development/development-tools-guidelines/infrastructure-charges




                                                                                                            Page 4 of 5
Document Set ID: 23690367
Version: 4, Version Date: 16/04/2025

Page 5

                 7. REFERENCE DOCUMENTS

                  Plan No.       Rev.     Plan/Document Name                                Date

                  241071         -        Flood Storage Calculations                        no date
                                          Prepared by Lindsay Consulting

                  24-1071-       A        Flood Storage Model Site Plan                     29 December 2024
                  F1
                                          Prepared by Lindsay Consulting

                  24-1071-       A        Flood Storage Model Perspective View                 29 ecember
                  F2                                                                              2024
                                          Prepared by Lindsay Consulting

                 8.     PROPERTY NOTES

                 Not applicable.
                 9.     VARIATION APPROVAL DETAILS

                 Not applicable.
                 10.    FURTHER DEVELOPMENT PERMITS REQUIRED

                  Type of Development Permit Required                Subject of the required Development Permit

                  Development          Permit      for   Operational Driveway crossover.
                  Works

                  Development Permit for Building Works              All building work.

                 11.    SUBMISSIONS

                 Not applicable.
                 12.    REPRESENTATIONS ABOUT REFERRAL AGENCY RESPONSE

                 The applicant may make representations to Council about this referral agency response at
                 any time before the application is decided pursuant to section 30 of the Development
                 Assessment Rules.
                 13.    OTHER DETAILS

                 If you wish to obtain more information about the decision, electronic copies are available online
                 at www.noosa.qld.gov.au or at Council Offices.


                 Yours faithfully,



                 Tiani Bird
                 Development Planner

                 Enc:   Approved Plans/Documents




                                                                                                           Page 5 of 5
Document Set ID: 23690367
Version: 4, Version Date: 16/04/2025

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.