Council archive · source document
Referral Agency Response - Planning RAP24 0038 (As Published) · DBW24/0122
Plan No. Rev. Plan/Document Name Date
WD.2.01 I Site Plan, prepared by Garland Design 27/02/2025
Annotated by Council
WD.2.03A I Ground Floor Plan, prepared by Garland 27/02/2025
Design
WD.2.04 I Level 1 Floor Plan, prepared by Garland 27/02/2025
Design
WD.2.07 I Roof Plan, prepared by Garland Design 27/02/2025
WD.3.01 I Elevations, prepared by Garland Design 27/02/2025
WD.3.02 I Elevations, prepared by Garland Design 27/02/2025
Building Height
3. The maximum height of the development must not exceed 8 metres above the ground
level.
4. Certification must be submitted to Council from a Registered Cadastral Surveyor (Qld)
which certifies that the building does not exceed the maximum height requirement of this
Decision Notice.
Noosa Waters Setback
5. The area within 4.5 metres of the centre line of the top of the concrete revetment wall
must be developed in accordance with the following:
(a) A minimum of 25% of the area must be planted with shrubs and small trees with a
mature height of 3m or less.
(b) A maximum of 25% of the area may be impervious, with the balance area soft
landscaping (i.e. grass, ground covers, shrubs and small trees).
(c) The ground surface within 1 metre of the revetment wall must be grass or ground
cover and must not include shrubs or hard pavement.
(d) Any side boundary fencing must taper down to a maximum height of 1.2 metres at
the revetment wall and have a height not exceeding 1.5 metres at a distance of
2.25 metres from the revetment wall.
(e) Any retaining structures, planter boxes or the like must be finished with natural
materials such as timber or rock rather than manufactured materials.
6. No shore side anchor points are permitted within 4.5m of the revetment wall.
Bonds
7. A site compliance bond of $5,000 is to be submitted to Council prior to the
commencement of works. The commencement of works can only commence once
Council's Construction Engineering Officer has confirmation that the bond monies have
been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance
with these conditions or any additional inspections incurred for substandard work or work
undertaken not in accordance with this permit.
Page 2 of 5
Document Set ID: 23690367
Version: 4, Version Date: 16/04/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.