Referral Agency Response - Planning RAP24 0038 (As Published) · DBW24/0122
8. Bonds must:
(a) Meet the requirements of council’s relevant Planning Scheme Policy for
performance and uncompleted works;
(b) Be lodged with Council and accompanied by the Bond Administration Fee/s; and
(c) Be requested for release by writing to Council, when relevant approval
requirements have been met.
Earthworks
9. All earthworks and associated retaining structures/batters must be contained entirely
within the subject site unless written permission from the respective landowner(s) is
provided to Council. All earthworks must be undertaken in accordance with the
provisions of Australian Standard AS3798: Guidelines on Earthworks for Commercial
and Residential Developments.
10. Earthworks carried out on site must not affect the structural integrity of the revetment
wall, existing fences or other structures that border the subject site. Fences that are
affected must be replaced in a timely manner and in consultation and agreement of the
owners of the related properties.
Revetment Wall / Flood Storage
11. All works within the 4.5m setback from the revetment wall must be carried out generally
in accordance with Linday Consulting’s Flood Storage Model Site Plan (24-1071-F1,
Rev. A) and Flood Storage Model Perspective Model (24-1071-F2, Rev. A) dated 29
December 2024.
12. All works for the purpose of increasing available flood storage must be located within
the 4.5m setback from the revetment wall.
13. Certification of the completed works within the 4.5m setback from the revetment wall
must be submitted to Council within 3 months of the completion of the works. The
certification must be prepared by a RPEQ (Registered Professional Engineer of
Queensland) and state that the works:
(a) Have not reduced the amount of available flood storage within the 4.5m setback
from the revetment wall;
(b) Have not negatively impacted the stability of the revetment wall or negatively
impacted the associated membrane;
(c) Have not reduced the available flood storage within the lot from the profile as
described in The Noosa Plan 2020 – Low Density Residential Zone Code; and
(d) Meet the relevant conditions of this approval.
4. REASONS FOR REFERRAL AGENCY’S DECISION
The proposal is subject to specific built form parameters outlined in Noosa Plan 2020.
5. TIME LIMIT FOR MAKING FURTHER APPLICATION
Pursuant to section 54(4) of the Planning Act 2016, you will not be required to refer your
building works application to council for a further Referral Agency Response if:
(a) you submit this Referral Agency Response in its entirety, including all referenced plans
and documents, when making the application to the Assessment Manager; and
(b) there are no changes to the proposal that was presented to council with this referral;
and
Page 3 of 5