Extension of Currency Letter · 132008.175.03

of 3

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

Council Reference: 132008.175.02
Our Reference:     00475 L21 NG



9th July 2019



Chief Executive Officer
Noosa Council
Po Box 141
TEWANTIN QLD 4565


Attention: Development Assessment


Dear Sir/Madam


RE:     EXTENSION APPLICATION                             _______________________________
Development Approval for Material Change of Use of Premises for Multiple Dwelling (22 units)
situated at 16 Serenity Close, Noosa Heads, described as Lot 9 on SP195871.


Martoo Consulting has been engaged by CBD Settlers Cove Pty Ltd being the owner of the above site, to
request an extension to the currency period for the above development approval. The applicant seeks
to extend the relevant period by an additional 4 years to the 6th August 2023.

The background of the development application is detailed below:

        2003 – Master Plan approved for Settlers Cove site including Residential High Density along
         Serenity Close, Detached Housing lots along Grosvenor Terrace and public land dedications.

        August 2009 - Council approved an application for a Material Change of Use for a Multiple
         Dwelling of 22 Units under the Superseded Planning Scheme (Schedule to the Planning
         Scheme and Strategic plan 1997). (2008/175)

        January 2014 – Council approved an application to extend the relevant period of the existing
         approval until 6th August 2017.

        September 2015 – Council approved an application to extend the relevant period of the
         existing approval until 6th August 2019.


The current owner of the site now seeks approval to extend the current approval for a further 4 years
noting:

               CBD Settlers Cove Pty Ltd have started construction of units at Lot 7 with completion
                expected sometime late 2020.

               Following completion of Lot 7 construction of Lot 8 will commence with completion
                expected around March 2022.

               Following completion of Lot 8 construction of Lot 9 will commence with completion
                expected around March 2023 to 2024.

               The extended time frames are required due to the construction timetable and lead in time
                for each development.
Full text of the other 2 pages

Page 2

        Page 2

                The site is included in the Attached housing zone and Open space Conservation zone
                 and the existing unit development and built form is consistent with this zoning;

                The existing development yield is consistent with the current 2006 Noosa Plan;

                Future surrounding uses would not be affected by the development of the site for
                 residential purposes;

                The development approvals are consistent with Councils intentions for the area;

                The community is well aware that the site is approved for unit development; and

                The development was recently reviewed in 2015 as part of the previous extension
                 application.


STATUTORY REQUIREMENTS:

In accordance with Section 87 of the Planning Act 2016, in assessing an extension application, the
assessment manager may:

     87(1) When assessing an extension application, the assessment manager may consider any matter that
          the assessment manager considers relevant, even if the matter was not relevant to assessing the
          development application.

ASSESSMENT:

The current development approval was assessed and granted under the superseded planning scheme
prior to the current Noosa Plan. The proposal was reviewed against the 2006 Noosa Plan provisions
under the 2011 and 2014 application for extension of the relevant period, wherein it was determined
that the development form generally was consistent with the current requirements of the Noosa Plan
and the areas of non compliance were minor. The current approval is therefore consistent with the
current laws and policies.

The proposal has also been reviewed against the Draft New Noosa Plan which includes the site in the
high Density Residential and Environmental Management and Conservation Zone. The proposal is
generally consistent with the development parameters detailed in this draft Plan.

With regard to infrastructure charges, it is noted that as part of previous changes to the approvals and
extensions, infrastructure charges for missing networks have been charged.

The current proposal is generally consistent with the current planning scheme requirements and
policies and the current conditions protect the environmental considerations of the site. The general
community is also well aware that the site has a development approval for the site. The proposed
extension is considered to meet the criteria of the Act and the applicant therefore requests an
extension of the currency period for a further four years.


This development application has been prepared in accordance with the Planning Act 2016 and is
being submitted with the following attached:
        1.        The completed Council form.
        2.        Council’s application fee of will be paid electronically.


Please contact me if you require any further information and/or clarification.

Page 3

       Page 3




Yours faithfully,




Nadine Gorton
Senior Town Planner
martoo consulting pty. ltd


[OCR of page images]
@ Page3

Yours faithfully,

Nadine Gorton
Senior Town Planner
martoo consulting pty. Itd

Used in these records

About this file

File size
273 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Extension of Currency Letter.pdf · 273 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.