SUPERSEDED - Negotiated Decision Notice 132008 176 05

of 38

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

                        Hollow inspection and removal
                        (e)       After under scrubbing and clearing on non-habitat trees, an elevated work
                                  platform or cherry-picker will be used in conjunction with a chainsaw operator
                                  and suitably qualified fauna spotter/catcher to inspect and remove hollows a
                                  necessary prior to habitat tree felling.
                        (f)       When the fauna has been safely secured within its hollow (or compensatory
                                  habitat/nest box), the entire limb can then be placed in the cherry-picker bucket
                                  or lowered to the ground using ropes depending on the size of the limb.
                        (g)       The limb and/or compensatory habitat/nest box will then be placed in a cool,
                                  quiet location until translocation to the recipient habitat site, when at dusk the
                                  hollow entrance is re-opened to allow the fauna to emerge of its own accord.
                 73.    Any proposed new fencing to delineate boundary alignments, with the exception of pool
                        fencing directly around pool areas, must be constructed to allow for the movement of
                        fauna.
                 74.    Twenty (20) permanent artificial nesting boxes must be installed within the
                        Environmental Management and Conservation Zone to provide compensatory habitat
                        for arboreal mammals and hollow dependent avian species. The works must be
                        undertaken in accordance with an Operational Works approval.
                        Bushfire Management
                 75.    All works must be carried out in accordance with a Site Management Plan (or part
                        thereof) prepared by a qualified person* and endorsed through an Operational Works
                        approval. The Site Management Plan must incorporate all precautionary bushfire
                        obligations required to ensure landscape design measures are achieved that meet a low
                        fuel state at all times and provide management techniques for the development site
                        administrators to consider as part of the development construction and ongoing
                        maintenance.
                        *(Refer to Advisory Note)
                 76.    Certification must be submitted to Council from a qualified person* which certifies that
                        the development has been constructed in accordance with the bushfire management
                        conditions of this Decision Notice.
                        *(Refer to Advisory Note)
                 77.    A Bushfire Evacuation Plan for the site must be prepared by a qualified person* and
                        submitted to Council prior to the issue of any Development Permit for Operational Works.
                        *(Refer to Advisory Note)
                 78.    A copy of the Bushfire Evacuation Plan for the development must be provided to the
                        nearest fire authority.
                        Waste Management
                 79.    A Waste Management Plan must be prepared that details the type and quantity of waste
                        material that is likely to be generated by the development; where and how the waste will
                        be stored, disposed of and procedures for handling the waste. The Waste Management
                        Plan must be submitted and approved by Council prior to the issue of a Development
                        Permit for Operational Works.
                 80.    The developer must provide waste storage and disposal facilities in accordance
                        with Planning Scheme Policy 9 - Waste Management. The facilities must include an
                        impervious area, within the site, correctly sized for all refuse and recycling containers
                        and suitably screened from public places and neighbouring properties. A bin wash area
                        is required with a cold-water tap, hose and drain outlet connected to sewer, via a bucket




                                                                                                         Page 13 of 38
Document Set ID: 23613543
Version: 2, Version Date: 04/03/2025
Log in to download the original file

SUPERSEDED - Negotiated Decision Notice 132008 176 05.pdf · 2.3 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.