PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 9 MAY 2017
ii. Schedule of Works (SOW) Table
The SOW table includes information derived from the “excel based” Schedule of Works
Model (refer following sub-section iii) and must state the following for each item of future
trunk infrastructure identified on the PFTI maps:
unique map reference to cross reference the item shown on the PFTI maps;
brief description of the item;
estimated timing expressed in terms of specific years or time periods (e.g. 2016–2021);
and
establishment cost for land or works stated in current cost terms and be consistent with
the SPA definition of ‘establishment cost’.
The methodology for determining the future trunk infrastructure items for the Public Parks
and Land for Community Facilities network has been undertaken as follows:
1) Review of the current PIP was undertaken to identify the remaining uncompleted future
projects relating to District and Shire-wide functions per the revised DSS adopted by
Council on 16 February 2017. This review is provided in Attachment 1 where the
remaining PIP future items for transferring to the LGIP are highlighted.
2) These PIP remaining future items were then summarised and reviewed individually in
relation to their costing and proposed timing. This review is provided in Attachment 2
which details and explains the methodology used:
Park type and hierarchy
This provides the trunk items classification in accordance with the revised DSS
adopted.
Current PIP 2006 base costs and timing
The PIP costs previously underwent the full Queensland Competition Authority
assessment during the original PIP review and State Government’s approval and
are therefore considered as remaining suitable for the LGIP costing where no
newer information is available.
Proposed LGIP 2014 base costs and amended timing
The LGIP base cost estimates of future works items have either used:
o the current PIP cost indexed from 2006 to 2014 by the ABS Road & Bridge
index in accordance with the guideline; or alternatively
o based on newer planning documentation where available.
Additional information regarding costing of some specific items is provided as
follows:
o For future land new purchase proposals, the costs have been re-estimated
using an average dollar rate per hectare based on current land selling data
obtained from the “realestate.com.au” website and indexed back to the
2014 base date using the ABS Consumer Price Index in accordance with
the guideline. This is summarised as page 3 of Attachment 2.
o For the future land requirements proposed from existing Council owned
land, the re-estimated cost is the land valuation obtained from Council’s
land asset register and proportioned to the land area required.
Page 5 of 29
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.