SPA Decision Notice - 010.2010.00000100.001 [As Published] · MCU11/0053
2010/100
Infrastructure Contributions
37. The applicant must pay contributions towards trunk infrastructure in accordance with the
following Planning Scheme Policies and Council Policies:
(a) Planning Scheme Policy 12 – Public Open Space Contributions;
(b) Planning Scheme Policy 13 – Contributions in Lieu of Off Street Parking;
(c) Planning Scheme Policy 16 – Sewerage Headworks Contributions;
(d) Planning Scheme Policy 17 – Water Supply Headworks Contributions;
(e) Planning Scheme Policy 20 – Pathway Trunk Network Contributions;
(f) Council Policy – Rural Roadworks Contributions;
(g) Council Policy – Master Drainage Contributions.
For material change of use of premises approvals the contributions must be paid prior to the
commencement of use, for reconfiguring a lot approval contributions must be paid prior to
Council approval of the plan of subdivision.
The actual amount of the contribution must be calculated and paid in accordance with the Planning
Scheme Policies and variations due to indexation current at the time of payment.
General Engineering Requirements
38. A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
specifications for all engineering works that will become Council infrastructure, which shall be
submitted in conjunction with an application for a Development Permit for Operational Works.
In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be
submitted in conjunction with any application for Operational Works.
39. Digital detailed designs including drawings, calculations, specifications etc, shall be submitted
with any application for a Development Permit for Operational Works in respect of roadworks
and stormwater drainage works. The design shall be in accordance with Council’s Planning
Scheme Policy PSP05 – Engineering Design Standards – Roads, Drainage and Earthworks.
To avoid conflict with underground pipes or services, all existing and proposed services
required by the development shall be shown on the plans.
40. To facilitate production of As Constructed drawings it is suggested that all design drawings are
submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the
use of ADAC are available at www.adac.com.au).
41. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
42. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
43. As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
for design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and
type of all services and structures. All of which shall be submitted to Council for checking and
for Council’s records.
The data must fully detail levels for all engineering works including but not limited to drainage
structures, finished ground levels and pavement surface levels. The data shall be submitted in
the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC
are available at www.adac.com.au).
Approval of works shall not be granted until all As Constructed information has been supplied
and accepted by Council.
Page 7 of 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SPA Decision Notice - 010.2010.00000100.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 79 KB (small file)
- File type
No other editions are linked here.