Reconfigure a Lot Conditions
1. For the purpose of these conditions, the following definitions apply: -
A Plan of Survey means the plan for the reconfiguration of a lot required to be endorsed by Council
pursuant to S3.7.1 of the Integrated Planning Act 1997.
2. Pursuant to Section 3.5.21(5) of the Integrated Planning Act 1997, the currency period is two (2) years
from the day this permit takes effect during which time all conditions must have been complied with and
the Plan of Survey lodged with the Council for endorsement.
3. In conjunction with the lodgement of the Plan of Survey for Council endorsement, legal documentation
shall be presented to Council and shall be submitted in the correct form with the fees prescribed in
Council's adopted fee schedule.
4. Pursuant to Section 3.7.3(c) of the Integrated Planning Act, all outstanding rates and charges due and
payable to Noosa Council in respect of the lots being reconfigured shall be paid prior to endorsement of
the Plan of Survey for each stage.
5. Prior to undertaking any excavation, the person acting on this permit shall contact public utility service
providers to ascertain the location of their underground services.
6. The person acting on this permit shall apply and obtain for all other necessary permits including crane
permits, road opening permits, hoarding permits, footpath occupation permits and/or any other approvals
required under any other Act.
7. Prior to commencement of work relating to a Development Permit for Operational Works, the Applicant
shall sign a written undertaking to be responsible for the full cost of repairs to road pavement, footpath,
kerb and gutter, or other Council property damaged as a result of construction of the proposed
development.
If any person acting under this permit damages any Council property or facilities (such as underground
drainage, water supply and sewerage) , through any cause whatsoever in the course of, directly or
indirectly carrying out development, that person shall forthwith notify the Manager - Land Development
and shall forthwith rectify that damage at its cost and to the satisfaction of the Manager - Land
Development. Alternatively, the Applicant may request the Council to carry out the rectification works.
Any damage to a water main shall be rectified by Council. Any damage to a sewer main shall be
undertaken by either Council or a Council approved contractor.
In all cases, Council reserves the right to carry out rectification works in an emergency and where no
reasonable attempt has been made to complete the rectification works as part of the development.
All costs incurred by Council in any rectification works shall be repaid to Council prior to the endorsement
of the Plan of Survey.
8. Prior to commencement of the permitted use the person acting upon this permit shall demonstrate the
legal right to the easement for access over Lot 65 on RP 52918. Where no legal right exists, this permit
shall lapse.
9. Prior to the endorsement of the Plan of Survey, the Applicant's Solicitor shall give Council's Solicitor an
appropriate undertaking in writing that in conjunction with lodgement of the Plan of Survey at the Land
Titles Office, the Title Deed and the easement documents will also be lodged and any additional Titles
Office forms or requisitions requiring the consent of Council being attended to forthwith.
SEP o:\database\onestop\decision.doc
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED COMPILED Decision Notice [As Published]Related documentApplication case desk ↗
About this file
- File size
- 50 KB (small file)
- File type
No other editions are linked here.