Information Request - 2212-32529 SRA

Attached to the e-mail MCU22/0203 OPW22/0304 - SARA Information Request—Noosa Spit Coastal Protection Works.

of 4

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                                                          2212-32529 SRA




         response to an information request for a previous development application for the proposed
         project. It is also noted that the Noosa Spit Coastal Protection Environmental Assessment
         prepared by BMT Commercial Australia Pty Ltd, dated 23rd November 2022, reference
         R.A10342.002.01_Environmental Assessment.docx and revision 01 states that dredging will be
         undertaken in winter months when shorebird numbers are lowest, but does not specify the
         months. Therefore, SARA seek to confirm the proposed dredge timing.
         Action:
         Confirm when you intend to undertake dredging, for example between April and September.


How to Respond
You have three months to respond to this request and the due date to SARA is 13 April 2023.

You may respond by providing either: (a) all of the information requested; (b) part of the information
requested; or (c) a notice that none of the information will be provided. Further guidance on responding to
an information request is provided in section 13 of the Development Assessment Rules (DA Rules).

It is recommended that you provide all the information requested above. If you decide not to provide all
the information requested, your application will be assessed and decided based on the information
provided to date.

You are requested to upload your response and complete the relevant tasks in MyDAS2.

As SARA is a referral agency for this application, a copy of this information request will be provided to the
assessment manager in accordance with section 12.4 of the DA Rules.

If you require further information or have any questions about the above, please contact Cavannah
Deller, A/ Senior Planning Officer, on 07 3244 9343 or via email [email protected]
who will be pleased to assist.

Yours sincerely




Paul Gleeson
Principal Planning Officer

cc        Noosa Shire Council, [email protected]


 Development Details

 Description:               Development Permit          Material Change of Use for Environmentally Relevant Activity (ERA) 16(1)(c) –
                                                         Extractive and Screening
                                                        Operational Work for Prescribed Tidal Works

 SARA Role:                 Referral Agency

 SARA Trigger:               Schedule 10, Part 5, Division 4, Table 2, Item 1 of the Planning Regulation 2017 (10.5.4.2.1) –
                              Environmentally Relevant Activity (ERA)
                             Schedule 10, Part 6, Division 3, Subdivision 3, Table 1, Item 1 of the Planning Regulation 2017 (10.6.3.3.1.1)
                              – Operational work involving removal, destruction or damage of marine plants




State Assessment and Referral Agency                                                                                           Page 3 of 4
Log in to download the original file

Information Request - 2212-32529 SRA.pdf · 216 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.