Information Request - 2212-32529 SRA
Attached to the e-mail MCU22/0203 OPW22/0304 - SARA Information Request—Noosa Spit Coastal Protection Works.
2212-32529 SRA
response to an information request for a previous development application for the proposed
project. It is also noted that the Noosa Spit Coastal Protection Environmental Assessment
prepared by BMT Commercial Australia Pty Ltd, dated 23rd November 2022, reference
R.A10342.002.01_Environmental Assessment.docx and revision 01 states that dredging will be
undertaken in winter months when shorebird numbers are lowest, but does not specify the
months. Therefore, SARA seek to confirm the proposed dredge timing.
Action:
Confirm when you intend to undertake dredging, for example between April and September.
How to Respond
You have three months to respond to this request and the due date to SARA is 13 April 2023.
You may respond by providing either: (a) all of the information requested; (b) part of the information
requested; or (c) a notice that none of the information will be provided. Further guidance on responding to
an information request is provided in section 13 of the Development Assessment Rules (DA Rules).
It is recommended that you provide all the information requested above. If you decide not to provide all
the information requested, your application will be assessed and decided based on the information
provided to date.
You are requested to upload your response and complete the relevant tasks in MyDAS2.
As SARA is a referral agency for this application, a copy of this information request will be provided to the
assessment manager in accordance with section 12.4 of the DA Rules.
If you require further information or have any questions about the above, please contact Cavannah
Deller, A/ Senior Planning Officer, on 07 3244 9343 or via email [email protected]
who will be pleased to assist.
Yours sincerely
Paul Gleeson
Principal Planning Officer
cc Noosa Shire Council, [email protected]
Development Details
Description: Development Permit Material Change of Use for Environmentally Relevant Activity (ERA) 16(1)(c) –
Extractive and Screening
Operational Work for Prescribed Tidal Works
SARA Role: Referral Agency
SARA Trigger: Schedule 10, Part 5, Division 4, Table 2, Item 1 of the Planning Regulation 2017 (10.5.4.2.1) –
Environmentally Relevant Activity (ERA)
Schedule 10, Part 6, Division 3, Subdivision 3, Table 1, Item 1 of the Planning Regulation 2017 (10.6.3.3.1.1)
– Operational work involving removal, destruction or damage of marine plants
State Assessment and Referral Agency Page 3 of 4