Original source · versioned page text
Information Request - 2212-32529 SRA
Attached to the e-mail MCU22/0203 OPW22/0304 - SARA Information Request—Noosa Spit Coastal Protection Works.
2212-32529 SRA
dated 05/01/2023 and reference M.A10342.001_Revised-Design-Drawings-and-Dredge-
Volumes, indicates that the project will involve dredging up to 136,000 tonnes within the ‘dredge
channel’ but the total amount of material required for the sand plugs and beach nourishment is
144,500 tonnes. Therefore, it is unclear where the remaining 8,500 tonnes of material will be
sourced and the characteristics of the material.
This information is required for SARA to determine compliance with PO8 and PO13 of State
Code 8 of SDAP.
Action:
Demonstrate that material from an alternative source to the ‘dredge channel’ is suitable for beach
nourishment and construction of the sand plugs. In particular, confirm the following:
the source of the 8,500 tonnes of material which is unaccounted for
the characteristics of the material and whether it matches the receiving environment in
terms of type and size
that the material does not contain contaminants at unacceptable levels
that the material is appropriate for the proposed use.
Volume of Dredge Material
3. Issue:
Based on the information provided, the amount of material to be dredged is unclear. Specifically,
the Noosa Spit Coastal Protection Environmental Assessment prepared by BMT Commercial
Australia Pty Ltd, dated 23rd November 2022, reference R.A10342.002.01_Environmental
Assessment.docx and revision 01, indicates that the project will involve:
dredging up to 85,000m3
14,000m3 of sand to fill the northern sand plug
17,000m3 of sand to fill the southern sand plug.
However, contradicting this, Table 1.1 Summary of volumes and tonnages of the Memorandum
prepared by BMT Commercial Australia Pty Ltd, dated 05/01/2023 and reference
M.A10342.001_Revised-Design-Drawings-and-Dredge-Volumes, indicates that the project will
involve:
dredging up to 80,000m3
11,450m3 of sand to fill the western sand plug
10,85m3 of sand to fill the eastern sand plug.
Action:
Confirm the exact volume of material to be dredged and the volume of fill required for each sand
plug in tonnes.
Note: The total volume of material should inform your response to Item 2 of this request.
Timing of Dredging
4. Issue:
The Letter prepared by BMT Commercial Australia Pty Ltd, dated 23 November 2022 and
reference L.A10342.002.01.Information Request Response.docx, indicates dredging will most
likely be undertaken between April and September.
Whilst this letter has been provided as part of the application material, it is noted this was a
State Assessment and Referral Agency Page 2 of 4
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original