GENERAL COMMITTEE MEETING AGENDA                                                  13 MARCH 2017


Hutchinson Builders tender submission is favourable as they have significant previous experience
with the design and construct delivery method, an excellent track record with similar projects, they
are more than capable and have the necessary resources to meet Council’s program to complete
these works by the 24th November 2017.

4.    Programme & Next Steps

Pending Council approval, Hutchinson Builders propose to construct the project including wet
weather allowances within 34 weeks, targeting practical completion before 24 November 2017.

5.    Construction Management and Inspections

Under the design and construct delivery model, Council will maintain the overall project
management role supported by externally appointed superintendent and specialist engineering
consultants to administer the contract and progressively inspect the works ensuring the project
objectives are met.

6.    Delivery
The delivery process involves the following key steps;
 Contractor finalising designs;
 Contractor obtaining all approvals including operational works, building and plumbing
   approvals;
 Contractor taking possession of site;
 Preparing site including reconstruction of car park;
 Construction of building including all services (excludes fit out);
 External landscaping;
 Commissioning and handover.

Finance & Risk

Council has allocated a total of $3,000,000 (excluding GST), with $1,000,000 in the 2016/17 capital
works budget and a further $2,000,000 identified in the draft 2017/18 capital works budget with
$13,486 spent to date. The budget for the design and construction of Peregian Beach Digital Hub
Building & Carpark works is sufficient to complete the project. Refer below table.

Council has been successful in receiving a grant for $1,008,000 from the State Government for
this project.

                          Item                              Cost

 Costs to Date (Jan 2017)                                      $13,486
 Tendered Contract Value                                    $2,727,461
 Council Project Manager                                       $20,000
 Superintendent                                                $40,000
 Engineering consultants (ICT, Electrical, Mech)               $20,000
 Developer Contributions from MCU                              $64,576
 Qleave (on $2.8M)                                             $13,775
 Subtotal                                                   $2,899,298
 Contingency                                                  $100,000
 Total                                                      $2,999,298
 Project Budget                                             $3,008,000


                                                                                      Page 5 of 34
Log in to download the original file

2017-03-13 General Committee Agenda(PDF, 4MB).pdf · 4.5 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.