GENERAL COMMITTEE MEETING AGENDA                                                  13 MARCH 2017


Risk

Finance risks include;
 Client request for scope changes. This is to be mitigated through project control group
   management and limitation of client requested scope variations.
 Latent conditions. Typically a geotechnical risk, previous investigations have mitigated much
   of this risk.
 Costs relating to service connections such as Energex and Unity Water. Mitigated through
   allowances based on industry experience.
 Variation risks. This has been partly mitigated through the lump sum design and construct
   procurement method with further mitigation through post tender clarifications tying Hutchinson
   Builders firmly into the scope of works.
 Contingency amount being insufficient. This risk may be mitigated through the adoption of
   saving options negotiated with Hutchinson Builders with further value engineering to occur
   during the detailed design process.

Time risks include;
 Wet weather delays. Construction during the typically dry season aims to mitigate this.
 Delays in obtaining approvals.
 Delays from specialist equipment such as lifts.

Safety Risks;
 Hutchinson Builders would be appointed as the Principal Contractor and responsible for
   Workplace Health and Safety of the site and the ultimate design. Prior to construction
   commencing, workplace health and safety and pedestrian and traffic management plans will
   be required to be submitted to Council for approval. Regular audits on contractor compliance
   with these approved plans will be undertaken by Council throughout construction.

Scope & Quality Risk;
 The risk of meeting project objectives is to be managed through Council staff reviews supported
   by specialist consultants who developed the engineering performance specifications.

Resource Risk;
 Hutchinson Builders have nominated a very capable team for this project limiting the resourcing
   risks to the project. The addition of external superintendent and engineering consultants,
   mitigates the resourcing risk from Council.

External Consultation - Community & Stakeholder
Extensive community consultation has been undertaken for this project and site in general. The
Peregian ‘Your Say’ site has a specific page dedicated to informing the community of progress and
updates to the project. This consultation tool will be supplemented during construction with project
news at the appropriate times through the project.
Immediately affected stakeholders will also be directly consulted during the works.

Internal Consultation
Rufous Street Project Control Group, Finance, Procurement, Environment, Civil Operations and
Asset Planning Teams.




                                                                                      Page 6 of 34
Log in to download the original file

2017-03-13 General Committee Agenda(PDF, 4MB).pdf · 4.5 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.