132005.699.1.05 - Application to Change to Existing Approval - (shows as 699.1.05 but should be .66.05) · 132005.699.04
132005.699.5
52. To ensure polluted run-off does not enter any of the proposed Infiltration Pits, and
ultimately the water table, stormwater run-off from the carparking areas and the
driveways shall have the first flush (the first 12 mm of rainfall or hose-down) collected in
a grease/oil arrestor (or similar device) provided on site prior to discharging into the
infiltration pits.
To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil
arrestors, which shall be submitted to the Council for approval prior to obtaining a
Development Permit for Operational Works.
The approved maintenance plan shall be incorporated in the Community Management
Scheme for the development and a copy of this shall be provided for Council's records
prior to commencement of the approved Use.
All other clean stormwater, such as roof water, can be collected on site and discharged
directly into the infiltration pits, bypassing the grease/oil arrestor.
A Development Permit for Building Works shall not be granted until a Development
Permit for Operational Works has been issued in regard to the drainage scheme.
53. All site stormwater drainage shall be by means of a gravity system.
54. Plans of the entire on site drainage design shall be prepared by a Registered
Professional Civil Engineer and submitted to Council prior to obtaining a Development
Permit for Operational Works.
Sewer Mains
55. The site shall be connected to Council's existing sewerage reticulation systems and be
constructed in accordance with Council's standards and requirements at no cost to
Council.
Town Water Supply
56. The site shall be connected to Council's existing town water supply and be constructed
in accordance with Council's standards and requirements at no cost to Council.
57. Each water connection to the water reticulation system shall extend to the property
boundary and be metered. Where multiple units are served by a single service, multiple
water meters to each individual unit and for the body corporate shall be installed. All
fees for the supply of water meters shall be paid to the Council.
Service Easements
58. All existing and proposed easements within the site shall be shown on the plans
submitted for Operational Works / Building Works approval.
59. Registered easements shall be created over any Council service within the subject site
in accordance with Council's requirements (if not already created) and at no cost to
Council.
The Applicant's Solicitor shall give Council's Solicitor an appropriate undertaking in
writing that the Title Deed and the easement documents will be lodged at the Land Titles
Office and any additional Titles Office forms or requisitions requiring the consent of
Council will be attended to promptly.
A duly executed copy of the easement shall be submitted to Council for perusal prior to
the use commencing.
Any changes required by Council's Solicitor must be corrected immediately.
Page 8 of 15
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
132005.699.1.05 - Application to Change to Existing Approval - (shows as 699.1.05 but should be .66.05)Related documentApplication case desk ↗
132005.699.1.05 - Application to Change to Existing Approval - (shows as 699.1.05 but should be .66.05)Related documentApplication case desk ↗
About this file
- File size
- 4.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.