Installation Guide - Load Support _v2021.3a
Infill Placement
Before Operating Vehicles on the Cells
1. Before construction vehicles go over Neoloy Tough-Cells,
ensure the following:
a) Minimum overfill (above cell) of 7 cm is required.
b) Verify that the outside border cells are completely
covered with infill.
c) Minimize turning, avoid sudden braking and limit
speed to less than 15 km/h.
d) No vehicle (or pavement layer) is permitted over
exposed cells.
FIGURE 17. SPREADING INFILL
Place Infill
1. Mechanically (or manually if necessary) infill the first
(outer) rows of the expanded sections using the
designated granular fill material according to the
construction plans.
NOTE: Limit drop height of infill to 1m (100 cm) to
prevent damage to the cell walls.
2. Overfill the Neoloy Tough-Cells to at least 7 cm above the
cell walls.
a) This is to allow for settling before trafficking or
compacting.
FIGURE 18. INFILL PLACEMENT
3. Continue infilling in the direction of the road.
a) Use the loader blade (back of shovel) to compact the infill.
NOTE: Visually inspect infill and remove any large pieces of debris, soil or rock – larger than one cell – to
prevent damage to the cell walls.
4. Manually spread the infill if necessary, to ensure uniform infill and that no cell walls are exposed. Do not walk on
empty cells. Use planks or boards to walk over empty cells.
5. After infill is complete, remove stakes/anchors before compacting.
a) Stakes/anchors may be reused.
PRS-EN-TD-LS-3000 13/21 Ver. 2021.3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Installation Guide - Load Support _v2021.3a.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.