ORDINARY MEETING MINUTES 20 AUGUST 2020
contain provisions requiring strict compliance by the owners and occupiers of the
proposed lots with the approved FEMP and the maximum building height requirements.
The community management statement must be submitted to the Council at the time of
sealing of the plan of survey.
Owners responsible for Body Corporate
33. The owners of the proposed lots, including successive landowners must, jointly and
severely, ensure that the requirements of these conditions to be carried out by the Body
Corporate or for which the Body Corporate is responsible, are complied with.
Water & Sewer Connections
34. An underground connection to reticulated water and sewerage must be provided to each
lot in accordance with the standards and requirements of Northern SEQ Distributor–
Retailer Authority (Unitywater).
35. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
(Unitywater) must be submitted to Council that certifies an underground connection to
reticulated water and sewerage has been provided to each lot OR the development site
(for MCUs).
Boundary Encroachments
36. Certification must be submitted from a Licensed Surveyor which certifies that:
a) the setback/s to any new boundaries for any existing buildings remaining on the
site comply with the relevant provisions of the planning scheme and the Building
Act 1975, unless varied by the development approval;
b) the constructed access and manoeuvring areas (including associated fill batters
and retaining walls) are fully contained within common property, including the 6m
wide by 8m deep turnaround bay required to facilitate efficient access and egress
for emergency services;
c) the fire trail and easement are established inside the perimeter of the Bushfire
Protection Zone on proposed Lot 1;
d) all utility services and connections (e.g. electricity, telecommunications, water,
sewerage) are wholly located within the lot they serve or alternatively included
within an easement;
e) all retaining walls and structures are fully contained within the lot they retain; and
f) any fill, including fill batters, are wholly contained within the subject site and not on
adjacent properties.
Electricity and Telecommunication Services
37. Underground reticulated electricity and telecommunication services must be provided to
each lot in accordance with an approval for Operational Works and the standards and
requirements of the relevant service provider.
38. Unless otherwise stipulated by telecommunications legislation at the time of
construction, the development must be provided with all necessary conduits, pits and
pipes to accommodate the future connection of optic fibre technology
telecommunications.
39. Certification must be submitted to Council from all relevant service providers which
certifies that the development has met the requirements of this Decision Notice and all
applicable legislation at the time of construction.
Page 15 of 16
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.