Attachment 7 - Energex Consent

of 6

Page text shows just the words. Original shows the document exactly as it was published.

                                                    5




   Access to the easement and access along the easement must be available to Energex
    personnel, including vegetation crews and regular routine line inspection crews, and
    heavy equipment, such as Heavy Trucks, Machinery and Cranes for construction,
    maintenance and emergency services, at all times.

   Existing access tracks must be re-instated, repaired or maintained if they are damaged
    during construction or other activities.

   Energex will require the Developer / owner to supply and install gates where fencing
    prohibits access to and along the easement area. To enable travel along the easement
    at anytime the gates must be series locked with an Energex padlock. Both the padlock
    and a design drawing of an acceptable gate will be provided by Energex.

   Lighting structures are not permitted in the easement without prior written consent of
    Energex. Lighting designs for proposed developments (e.g. road, carparks etc) on the
    easement are likely to require reduced height structures. Please submit detailed design
    to Energex for approval. These drawings must clearly show the following;
            a. Proposed height of the lighting structures and the ground level at the
                structure base,
            b. Relative (to lighting structures) ground levels at Energex structures (towers,
                pole etc) either side of the lighting structures, and
            c. The location of the Energex structures in relation to the proposed lighting

   Pools and structures (including lighting structures) or metal fences are not
    permitted to be installed on or near Energex easement without prior approval or
    notification.

   Rubbish, materials and / or tall equipment such as cranes and excavators are not
    permitted to be stored or used on the easement.

   Excavations or mounding of material under or close to conductors or Energex
    structures is not permitted.

   Energex must be notified of construction on or near the easement, conductors or
    structures prior to commencement of construction.

   All construction work must be clear of the easement unless construction risk hazard
    is identified. High voltage clearances must be maintained prior to construction
    commencing.

   Warning signs may be required during and after construction.

         Consideration must be given to the type of vegetation planted in Park Areas
          within and near the Energex easement. Any proposal for landscaping on the
          easement must have prior approval from Energex. Please submit the relevant
          landscaping design to Energex for approval. When considering landscape designs
          the planting of trees must be kept to the edges of the easement and not under any
          overhead conductors. When mature, plants or trees must not grow in excess of
          3.5 metres in height. Please visit https://www.energex.com.au/home/safety/safety-
          around-the-network/safetree-plants for a full list of safetree plants.



Reference: HBD 6804682

                             Did you know Energex has a referral website?
        https://www.energex.com.au/home/our-services/connections/development-application-referrals
Log in to download the original file

Attachment 7 - Energex Consent.pdf · 273 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.