NOOSA COUNCIL IDAS Development Application Decision Notice 7 of 16
Earthworks
50. Filling works required on site shall be carried out in accordance with Section 3.8 of Council’s Engineering
Design Standards Manual and so as not to cause the additional ponding of water on any adjoining lands
or the blockage of, or interference with, any natural watercourses.
This may require the design and construction of drainage pipes and/or an overland flow-path within the
development site that caters for drainage from the adjoining sites for a design storm with an Average
Recurrence Interval of 1 in 100 years. A private easement for the Drainage of Water encompassing the
drainage pipes or overland flow-path will also be required. In this regard a Development Permit for
Operational Works shall be obtained.
Should evidence be provided to Council indicating that no additional ponding of stormwater will occur on
the adjoining properties the requirement for the drainage pipes, overland flow-path and easement shall
not apply.
51. Earthworks carried out on site shall not affect the structural integrity of any of the existing fences or
structures that border the development site. Fences that are affected shall be replaced prior to the
Building Certifier issuing the Certificate of Classification. In this regard any fences to be replaced shall be
clearly shown on the plans submitted for Operational Works approval.
Erosion and Sediment Control
52. Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
to the Council for approval prior to obtaining a Development Permit for Operational Works.
Contributions Towards Council Infrastructure
53. Monetary contributions shall be paid to Noosa Council towards the cost of providing and/or upgrading
various infrastructure at the rates applicable at the time of payment. An estimate only of the contribution
amounts under the current Council policies and requirements is outlined in the table below:
Contribution Required For: Amount:
PSP13 – Contributions in Lieu of the Provision of Off-Street Parking (3 spaces)
$35,808
PSP16 – Sewerage Headworks Contributions $13,517
PSP17 – Water Supply Headworks Contributions $7,643
TOTAL Contribution Amount = $ 56,968
Please note, that these amounts are all subject to variations in the Consumer Price Index, All Groups Brisbane
from March 2007 until the date of payment.
All contributions must be paid prior to the issue of a Development Permit for Operational Works.
Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should the contributions
not be paid at the due time, Council shall call upon the trading bank guarantee in full.
Processing of bonds for security where specific Council approval has been given for the bonding of
contributions will incur an administration fee in accordance with Council’s Land Development Commercial
& Regulatory Fees at the time of lodgement.
In the event that the Development Permit for Material Change of Use of Premises lapses or is cancelled,
the trading bank guarantee will be returned.
General
54. A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
specifications for all engineering works that will become Council infrastructure, which shall be submitted in
conjunction with an application for a Development Permit for Operational Works. In this regard a
DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be submitted in conjunction
with any application for Operational Works.
55. Digital detailed designs including drawings, calculations etc, shall be submitted with any application for a
Development Permit for Operational Works in respect of roadworks and stormwater drainage works. The
design shall be in accordance with Council’s Planning Scheme Policy PSP05 – Engineering Design
Standards – Roads, Drainage and Earthworks. To avoid conflict with underground pipes or services, all
existing and proposed services required by the development shall be shown on the plans
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@8c06eccd\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - 010.2006.00000718.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 239 KB (small file)
- File type
No other editions are linked here.