NOOSA COUNCIL IDAS Development Application Decision Notice                                                   6 of 9


      A report of the CCTV inspection, including photographic records (which includes photos & video
      recordings burnt onto a CD) of the inspection shall be submitted to the Council for approval. Any defects
      or substandard works shall be recorded and accurately illustrated on the drainage plan showing the
      location of the defect(s).
      Substandard work will not be accepted ‘On Maintenance’ and must be rectified at the applicants expense
      with a further CCTV inspection arranged once the rectification works have been completed.
      To this extent all CCTV inspections, including any additional inspections necessary following defect
      identification and rectification, shall be entirely at the applicant’s expense. Any costs incurred by Council
      in reviewing the CCTV inspection results shall also be borne by the applicant.

37.   Certification of the completed works must be provided by the supervising engineer, together with
      certification from the Hydraulic Engineer that the completed works conform with all aspects of the
      drainage design for the development.

38.   Prior to acceptance of civil works to become Council assets "On Maintenance", the lodgement of
      satisfactory “As Constructed” records shall be submitted to Council.

      As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer (RPEQ) for
      design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and type of all
      services and structures. All of which shall be submitted to Council for checking and for Council’s records.
      The data must fully detail levels for all engineering works including but not limited to drainage structures,
      finished ground levels and pavement surface levels. The data shall be submitted in the Asset Design and
      As Constructed (ADAC) digital format.            (Guidelines on the use of ADAC are available at
      www.adac.com.au) and Council’s Planning Scheme Policy 5 – Engineering Design Standards – Roads,
      Drainage and Earthworks.

      Approval of works shall not be granted until all As Constructed information has been
      supplied and accepted by Council.

39.   A 5% cost of works to become Council assets or $1,500 bond (whichever is the greater) will be imposed
      on construction works during the maintenance period, which is a minimum period of 12 months duration.
      Such bond must be lodged by, and shall only be accepted from the Developer for the works.

40.   The works to become Council assets will not be accepted "On Maintenance" until the landscaping is
      completed.

41.   These works are also to be in compliance with the relevant conditions of Development Permit No. 23737
      DA.

42.   Notwithstanding that Council has checked the plans with due care, where it is found during construction
      that variations from Council's standards exist, then Council standards shall apply.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@54044421\@[email protected]

Used in these records

About this file

File size
42 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

0015A787.001.pdf · 42 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.