NOOSA COUNCIL IDAS Development Application Decision Notice 5 of 9
25. The Consulting Engineers for the project shall be currently Registered Professional Engineers of
Queensland (RPEQ). The consulting engineers are responsible for arranging all inspections, with
Council’s Construction Technical Officer or nominated staff.
26. Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the project.
(This person will be the contact for the project).
27. Council standards shall apply to these works unless otherwise modified herein.
28. The person acting on this permit shall ensure that its consultants and contractors take all reasonable care
during the construction of the engineering works to ensure that Council property, road pavements or
facilities (such as underground drainage, water supply, sewerage, footpaths, kerbing, landscaping, street
furniture etc.) are protected against any damage or interference whatsoever.
If any Council property or facilities should be damaged by the Applicant or any of its Consultants or
Contractors through any cause whatsoever in the course of, directly or indirectly, carrying out the
engineering works, the Applicant and/or its Contractors shall forthwith notify the Manager Land
Development and shall forthwith rectify the damage to that property or facility at its cost and to the
satisfaction of the Manager Land Development.
All rectification works are to be completed prior to the commencement of the use or, alternatively, the
Applicant may request the Council to carry out the rectification work at the Applicant’s cost, such cost
being paid by the Applicant to the Council prior to the commencement of the use.
In the case of any emergency the Council shall be entitled to rectify such damage at the cost of the
Applicant, such cost being paid prior to the commencement of the use.
29. The development of the site shall be carried out in such a manner as to prevent dust and/or sand
nuisance to residents and/or tenants in the vicinity of the development.
30. Construction work and other associated activities are permitted only during the hours of 7.00 am and 6.00
pm Monday to Saturday. No work is permitted on Sundays or public holidays, except where extended
hours are approved by the Manager-Land Development or his nominee.
31. All signage, including that for safety during construction shall be in accordance with the Manual of Uniform
Traffic Control Devices and Traffic Infrastructure (Roads) Act.
32. Safe pedestrian access on Elizabeth Street shall be maintained at all times. Should footpath / road
closures be necessary to carry out construction works, Council’s Construction Technical Officer (ph 0410
512 505) must be notified prior to the proposed closure.
33. Sediment and erosion control measures must be in place prior to works commencing. If such measures
are not in place or are not satisfactory, “on the spot “fines may be issued. Such fines can be issued if
sediments from the site are found to enter or have the potential to enter Council’s stormwater system or
natural waterways. Although the sediment and erosion control measures have been approved on drawing
No 1740-0-2 dated 11/05/07 by Construction Hydraulic, Council’s Manager – Land Development may
request further controls to be installed should approved measures be inefficient.
34. The owners of the subject property shall maintain the grease/oil arrestor pits/gross pollutant traps in
accordance with the manufacturers specifications.
35. The owners of the subject property shall inspect the grease/oil arrestor pits/gross pollutant traps on a
weekly basis and after each storm event.
The owners of the subject property shall enter into an ongoing maintenance contract with a Registered
Contractor to clean and maintain the grease/oil arrestor pits/gross pollutant traps on a regular three
monthly cycle and on a “On Call” basis in the case of an emergency.
The management and maintenance of the grease/oil arrestor pits/gross pollutant traps shall be included in
the Community Management Scheme for the completed development.
36. All stormwater drainage lines including private drainage lines (also known as inter-allotment drainage
lines) or as otherwise approved by Council’s Manager of Land Development shall be inspected by closed
circuit television (CCTV) at the completion of all works and immediately prior to acceptance ‘On
Maintenance’. Council’s Construction Technical Officer shall be advised of the timing of this inspection.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@54044421\@[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
0015A787.001.pdfRelated documentPublic source context ↗
Decision Notice - 010.2007.00000836.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 42 KB (small file)
- File type
No other editions are linked here.