Approved Decision Notice - RAL22 0026

of 9

Page text shows just the words. Original shows the document exactly as it was published.

                      Property Access and Driveways
               18.    The residential driveway to Lots 1 & 2 Black Mountain Range Road must be constructed to
                      ensure that maximum sight distances can be achieved. The works must be undertaken in
                      accordance with an Operational Works approval and be generally in accordance with ALTA’s
                      Roadwork Driveway Details (A6682/22/P05) dated 28 November 2022 and Standard
                      Drawing RS-056.
               19.    Vehicle access to Lots 1 & 2 is limited to the constructed driveway only. A clause must be
                      included in the contract of sale for Lots 1 & 2 which requires vehicle access to be from the
                      constructed driveway only, and which prohibits the driveway from being relocated without
                      Council agreement.
                      Stormwater Drainage
               20.    Stormwater runoff from the development must be disposed of on-site without causing scour
                      or damage to the subject site or any adjoining property and be generally in accordance with
                      ALTA’s Roadwork Layout Plan (A6682/22/P03) dated 28 November 2022.
                      Services
               21.    Reticulated electricity and telecommunication services must be provided to each lot in
                      accordance with the standards and requirements of the relevant service provider.
               22.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               23.    Certification must be submitted to Council from all relevant service providers (Energex, NBN)
                      which certifies that the development has met the requirements of this Decision Notice and
                      all applicable legislation at the time of construction.
                      Easements
               24.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               25.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               26.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Geotechnical Stability - Subdivisional Requirements
               27.    All subdivisional works must be carried out in accordance with the recommendations
                      contained in section 4 of Tectonic’s Slope Stability Assessment (22328-001-Rev1) dated 17
                      November 2022.
                      Geotechnical Stability - Future Dwelling Requirements
               28.    All future dwellings on the approved lots must be sited and constructed in accordance with
                      the recommendations contained in section 4 of Tectonic’s Slope Stability Assessment
                      (22328-001-Rev1) dated 17 November 2022, unless varied by a site specific investigation
                      for a particular house lot.
               29.    All future dwellings on the approved lots must be sited within the building envelopes shown
                      on the Approved Plans.
                      Earthworks and Retaining Walls
               30.    All fill and associated batters must be undertaken in accordance with an Operational Works
                      approval, and contained entirely within the subject site unless written permission from the
                      respective landowner(s) is provided to Council.



                                                                                                       Page 5 of 9
Document Set ID: 22258580
Version: 2, Version Date: 18/01/2023
Log in to download the original file

Approved Decision Notice - RAL22 0026.pdf · 197 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.