Council archive · source document
SUPERSEDED SPA Decision Notice - 010.2010.00000871.001 [As Published] · 132010.871
2010/871
Plan / Document No. Issue. Plan / Document Name Date
0907 -DA100 A Site Plan - Teeland Architects May 2010
0907 -DA101 A Ground Floor Plan - Teeland Architects May 2010
0907 -DA102 A Upper Floor Plan - Teeland Architects May 2010
0907 –DA201 A North Elevation - Teeland Architects May 2010
0907 –DA202 A South Elevation - Teeland Architects May 2010
0907 –DA203 A East Elevation - Teeland Architects May 2010
0907 –DA204 A West Elevation - Teeland Architects May 2010
General
2. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
3. The developer must obtain all of the other Development Permits referred to in the Decision
Notice, prior to obtaining a Development Permit for Building Works.
Security Bond
4. Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must be
submitted, to secure performance of all conditions of this approval, prior to the issue of a
Development Permit for Operational Works. The cash bond or trading bank guarantee will be
returned on performance of the conditions of approval less any costs incurred by Council in
respect of enforcing performance of this permit.
5. The requirements of this development approval are to be effected, prior to the use of the
premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
this approval to effect compliance with conditions.
Relevant Period
6. The Development Permit for a material change of use lapses if the use has not happened by
12 November 2014, unless an application to extend the relevant period is approved by
Council.
Built Form
7. The development shall not exceed a maximum height of 8 metres above natural or finished
ground level.
8. A verification survey of the building is to be carried out by a licensed Surveyor and a certificate
lodged with Council at completion of work confirming compliance with the maximum allowable
building height.
9. Any deck or balcony areas are not to be enclosed with shutters, glass panelling or the like,
thus remaining as open structures.
Landscaping
10. The open space and setback areas are to be landscaped in accordance with Council’s Policy
on Landscaping Guidelines and a properly prepared landscape plan prepared by a suitably
qualified Landscape Architect or Horticulturalist. Such landscaping is to be completed prior to
the premises being occupied and maintained at all times thereafter.
11. The landscape plans required to be submitted are to denote areas of existing vegetation or
existing trees proposed or required to be retained and shall include:
11.1. The retention of four macadamia trees along the Kareela Avenue frontage;
Page 2 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED SPA Decision Notice - 010.2010.00000871.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 859 KB (small file)
- File type
No other editions are linked here.