SUPERSEDED Negotiated Decision Notice - 010.2010.00000811.001 [As Published] · 132010.811

of 17

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                              Officer:          Jack Lewis
                                              Direct Telephone: (07) 5449 5183
                                              Response Address: Locked Bag 72
                                                                Sunshine Coast Mail Centre QLD 4560
                                              Email:            [email protected]
                                              Our Reference:    2010/811
                                              Your Reference:   GIR:NR:8976/10
27 October 2010

Altum Constructions
CARE Rigby Lawyers
Suite 8 Noosa Professional Centre
1 Lanyana Way
NOOSA HEADS QLD 4567



Dear Sir

                              Negotiated Decision Notice
                                  Sustainable Planning Act 2009

I refer to your application and the representations you made in respect to the Decision Notice. On
25 October 2010 Council decided your representations.
Details of the negotiated decision are as follows:

1     APPLICATION DETAILS

 Application No:                   2010/811
 Street address:                   22 Tristania Drive MARCUS BEACH
 Real property description:        Lot 84 M11112
 Planning Scheme:                  The Noosa Plan

2     DECISION DETAILS
Council on 12 July 2010 decided to issue the following type of approval:-
    Development Permit for Material Change of Use - Multiple Housing Type 2 - Duplex
In relation to representations, Council decided to:
A.    Agree to amend Conditions 6 and 15.
B.    Issue a Negotiated Decision Notice.

3     RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager conditions.




                                                                                               Page 1 of 17
Full text of the other 16 pages

Page 2

                                                                                            2010/811



4     ASSESSMENT MANAGER CONDITIONS
Planning Assessment
General
1.    Development undertaken in accordance with this approval must generally comply with the
      approved plans of development. The approved plans are listed in the following table and as
      amended by these conditions.

      Plan / Document No.       Issue.    Plan / Document Name                            Date
      0912 - CD 1.01            P6        Site Plan Ground Floor – Middap Ditchfield      2 June 2010
                                          Pty Ltd
      0912 - CD 0.04            P2        Easements – Middap Ditchfield Pty Ltd           2 June 2010
      0912 - CD 3.01            P5        Site 22 Ground Floor Plan – Middap Ditchfield   2 June 2010
                                          Pty Ltd
      0912 - CD 3.02            P5        Site 22 First Floor Plan – Middap Ditchfield    2 June 2010
                                          Pty Ltd
      0912 - CD 3.03            P3        Site 22 Roof Plan – Middap Ditchfield Pty Ltd   2 June 2010
      0912 - CD 4.01            P3        East Elevation – Middap Ditchfield Pty Ltd      2 June 2010
      0912 - CD 4.02            P3        West Elevation – Middap Ditchfield Pty Ltd      2 June 2010
      0912 - CD 4.03            P3        South & North Elevation – Middap Ditchfield     2 June 2010
                                          Pty Ltd

2.    The development must be undertaken and operated in a manner that causes no detrimental
      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
      lighting nuisance or other emissions.
3.    Security in the form of a cash bond or trading bank guarantee to the sum of $10,000 must be
      submitted, to secure performance of all conditions of this approval, prior to the issue of a
      Development Permit for Operational Works. The cash bond or trading bank guarantee will be
      returned on performance of the conditions of approval less any costs incurred by Council in
      respect of enforcing performance of this permit.
4.    The requirements of this development approval are to be effected, prior to the use of the
      premises. Council reserves the right to call upon the bond or guaranteed sum referred to in this
      approval to effect compliance with conditions.
5.    The developer must obtain all of the other Development Permits referred to in the Decision
      Notice, prior to obtaining a Development Permit for Building Works.
6.    The Development Permit for a material change of use lapses if the use has not happened by
      25 October 2014, unless an application to extend the currency is approved by Council.
Building Design
7.    A verification survey of the building is to be carried out by a Licensed Surveyor and a certificate
      lodged with Council at completion of work confirming compliance with the maximum allowable
      building height of 8.0 metres, measures from existing and finished ground level.
8.    Any deck or balcony areas are not to be enclosed with shutters, glass panelling or the like, thus
      remaining as open structures.
9.    External colours and finishes of the building shall comprise muted/environmental tones that
      blend with the natural environment.
10.   Mechanical plant and equipment including pool and spa pumps, pool heaters, air conditioning
      units and refrigeration units shall be screened by fencing or with dense vegetation 1.5 metres in
      height. These shall be visually integrated into the line of the building and roof design and do not

                                                                                           Page 2 of 17

Page 3

                                                                                         2010/811



      project beyond the height or width of the building when viewed from the street or other
      properties.
Landscaping
11.   The open space and setback areas are to be landscaped in accordance with Council’s Planning
      Policy 3 - Landscaping Plants & Guidelines using suitable coastal species and a properly
      prepared landscape plan prepared by a suitably qualified Landscape Architect or
      Horticulturalist. Such landscaping is to be completed prior to the premises being occupied and
      maintained at all times thereafter.
12.   The landscape plans required to be submitted are to denote areas of existing vegetation or
      existing trees proposed or required to be retained and shall include:
      12.1. Native screening vegetation provided within garden beds with a minimum of 500mm
            width along the rear boundary;
                                                                               2
      12.2. Exclusive clothes drying areas with minimum dimensions of 25m ;
      12.3. Native landscaping to be provided (including the use of large trees equivalent to 60% of
            the height of the building on maturity) to screen the northern and southern boundaries of
            the site with adjoining buildings;
      12.4. A minimum of 2 x 45 Litre native street trees shall be established on the frontage within
            the road reserve and include the following species:
       SMALL STREET TREES IN COASTAL AREAS UNDER POWER LINES
        Acronychia imperforata                      Fraser Island apple
        Alectryon coriaceus                         Beach birds eye
        Acmena hemilampra                           Broad leafed lilly pilly
        Banksia aemula                              Wallum banksia
        Banksia integrifolia
        Casuarina glauca                            Swamp sheaok
        Elaeocarpus reticulatus                     Blue berry ash
        Eucalyptus bancrofftii                      Tumbledown gum
        Grevillea banksii                           Red flowering silky oak
        Petalostigma pubescens                      Quinine berry

13.   Existing trees on the site and within road reserves are to be retained, except where required to
      be removed due to building operations or the conduct of the approved use.
14.   Cleared vegetation is to be suitably processed by one of the following methods and removed
      from the site:-
      14.1. Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled
            loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a minimum
            of 10 metres between edges of heaps.
      14.2. Disposal for firewood.
      14.3. Disposal for landscaping purposes.
      14.4. Transport to alternative site for breaking down materials provided that all necessary
            permits have been obtained to allow the alternate site to be used for this purpose.
      14.5. The disposal method for clearing works is to be submitted in conjunction with an
            application for a Development Permit for Operational Work. The Applicant is advised that
            other methods may be considered provided full details of the method are submitted.
      The Applicant is advised that burning off is an unacceptable method of disposal.

                                                                                         Page 3 of 17

Page 4

                                                                                          2010/811



Fencing
15.   Front fences and walls are to be setback an average of 1 metre, which is articulated to provide
      visual interest by stepping the design at maximum 5m intervals. The area of land between the
      fence and the front property boundary shall be densely landscaped to screen any fencing from
      the street.
Noise Nuisance
16.   Noise emission from mechanical equipment shall comply with the following requirements:
      16.1. Air-conditioning and Refrigeration:
               7am to 10pm: Maximum background + 5dB(A)
               10pm to 7am: Maximum background + 3dB(A)
      16.2. Pumps:
               7am to 7pm: Maximum background + 5dB(A)
               7pm to 10pm: Maximum background + 3dB(A)
               10pm to 7am: No audible noise.
17.   Submission of written certification shall be provided from a suitably qualified person confirming
      that the noise levels from all mechanical equipment comply when measured at either the
      residential boundary or outside the most exposed part of an affected building, whichever is the
      closest to the equipment.
      The assessment and certification is required immediately after installation of the equipment and
      prior to any occupation of the building, and in a format approved by Council. All equipment
      should be operating at the same time to test the overall noise level created.
      Advice: It is highly recommended that the person you engage to certify the installation is
      involved at the plan development stage so they can recommend where this equipment is best
      located. They can also advise about noise enclosures and can make other suggestions to avoid
      noise problems. It is a lot more costly to try and deal with noise problems after everything is
      built.
18.   Noise from residential building works shall comply with the following –
      18.1. Limited to between 7:00am to 6:30pm Monday to Saturday.
      18.2. All reasonable measures are taken to minimise noise emissions.
      18.3. Not permitted on Sunday or public holidays.
Infrastructure Contributions
19.   The applicant must pay contributions towards trunk infrastructure in accordance with the
      following Planning Scheme Policies and Council Policies:
      (a)   Planning Scheme Policy 12 – Public Open Space Contributions;
      (b)   Planning Scheme Policy 13 – Contributions in Lieu of Off Street Parking;
      (c)   Planning Scheme Policy 16 – Sewerage Headworks Contributions;
      (d)   Planning Scheme Policy 17 – Water Supply Headworks Contributions;
      (e)   Planning Scheme Policy 20 – Pathway Trunk Network Contributions;
      (f)   Council Policy – Rural Roadworks Contributions;
      (g)   Council Policy – Master Drainage Contributions.
      For material change of use of premises approvals the contributions must be paid prior to the
      commencement of use, for reconfiguring a lot approval contributions must be paid prior to
      Council approval of the plan of subdivision.

                                                                                         Page 4 of 17

Page 5

                                                                                          2010/811



      The actual amount of the contribution must be calculated and paid in accordance with the
      Planning Scheme Policies and variations due to indexation current at the time of payment.
Operational Works Assessment
Vehicle Access
20.   A vehicular access driveway to serve the development on Lots 84 and 85 M11112 (Numbers 22
      & 20 Tristania Drive respectively) shall be constructed from the Tristania Drive frontage of the
      site generally as shown on drawing number Drawing No CD 1.01 P6 Project No 0912 dated 2
      June 2010 by Middap Ditchfield Pty. The first 6m of the driveway measured from the kerb line
      in Tristania Drive shall be 5.5m wide to allow for car passing opportunities.
21.   The driveway shall be designed and constructed to Council’s design standards and to grades
      that prevent vehicles from scraping and/or bottoming whilst also allowing pedestrians
      movements along the footpath without any step or level difference. Should any driveways be
      constructed to grades that do not comply with AS/NZS 2890.1-2004, Council will require that the
      driveway be removed and reconstructed to levels that do comply.
      Please note, a step between the driveway and the footpath shall be avoided, as it is preferred to
      have the footpath continue at a constant grade to minimise the potential for pedestrians to trip
      or fall.
Vehicle Access Easement
22.   A reciprocal vehicle access easement shall be created on Lots 84 and 85 M 11112 to
      encompass all the proposed driveway and vehicle turning areas generally as shown on Drawing
      No CD 0.04 P2 project No 0912 dated 2 June 2010 by Middap Ditchfield Pty Ltd.
      In this regard, plans submitted for Operational Works approval shall accurately show the
      location of the easement. In addition to this the Applicant’s Solicitor shall give Council’s
      Solicitor an appropriate undertaking in writing that the Title Deed and the easement documents
      will be lodged at the Land Titles Office and any additional Titles Office forms or requisitions
      requiring the consent of Council will be attended to promptly.
      A duly executed copy of the easement shall be submitted to Council for perusal prior to the use
      commencing. Any changes required by Council’s Solicitor must be corrected immediately. All
      legal and administration costs shall be paid by the developer.
Car Parking
23.   Carparking shall be provided within the site generally as shown on drawing number Drawing No
      CD 1.01 P6 Project No 0912 dated 2 June 2010 by Middap Ditchfield Pty Ltd, except as
      modified by these conditions.
24.   The driveway, garages and carparking areas shall be designed to comply with the provisions of
      AS/NZS 2890.1-2004 for user class 1A with allowance for vehicles to enter and leave the site in
      a forward gear in three movements, with a minimum head clearance (headroom) at any point of
      2.3m.
Frontage Works
25.   Footpath improvements such as topsoiling, grassing, and tree planting are required to the
      Tristania Drive frontage of the site in accordance with Planning Scheme Policy PSP03
      Landscaping Plants & Guidelines. Grass shall be couch, free of weeds.
26.   A new 1.5m wide concrete path shall be constructed along the Tristania frontage of the site in
      accordance with Council’s design standards and to an alignment that protects any significant
      vegetation or any underground services and to smoothly join any existing pathway.
27.   All paths, driveways and parking areas associated with this development shall be designed and
      constructed to ensure pedestrian safety using non-slip materials, to produce an evenly graded
      surface finish, and to be in accordance with the Disability Discrimination Act 1992 and
      Australian Standard 1428.1 - Design for Access & Mobility.



                                                                                         Page 5 of 17

Page 6

                                                                                          2010/811



28.   All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel,
      footpath paving and landscaping such as trees and grasses in accordance with Council’s
      Standard specifications prior to commencement of the use permitted by this permit.
Roof Water & Stormwater Drainage
29.   Roof runoff from any new building shall be directed to a rainwater storage system or tank that is
      installed within the property to ensure water from the rainwater storage system or tank is used
      for external uses (such as watering gardens, irrigation, ornamental ponds, water features,
      topping-up swimming pools, outdoor cleaning, etc) and for internal (ground floor) use in washing
      machine cold taps and toilet cisterns. All rainwater tanks are to be designed and installed in
      accordance with the Queensland Development Code (QDC) current at the time of building
      approval, and shall be part of the plumbing application for approval. The location and capacity
      of the tanks shall be clearly shown on the plans submitted for Building Works and Operational
      Works approvals and any overflow shall be discharged into the existing stormwater system
      (stormwater structure or kerb & channel) at Tristania Drive.
30.   All stormwater drainage (including roof water overflow from the rainwater storage system) shall
      be collected and discharged so there is no net increase in stormwater runoff from the site.
      Stormwater drainage permitted to drain from the site shall be discharged to Council’s: existing
      drainage system (kerb & channel or/and stormwater structures) in Tristania Drive generally as
      shown on drawing No 10031 -2 A dated 20 May 2010 by Ian Bradford. Detailed plans of the
      drainage design for operational works shall be prepared by a suitably qualified and experienced
      person and submitted to Council prior to obtaining a Development Permit for Operational
      Works.
      The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street
      drainage system at any one location is 25 litres/second.
31.   The development shall not cause diversion of stormwater or adversely impact on the existing
      drainage conditions on adjoining properties or the road reserve.
32.   To ensure that polluted run-off does not enter Council’s stormwater drainage system,
      stormwater run-off from the carparking areas and the driveways shall have the first flush (the
      first 12 mm of rainfall or hose-down) collected in a grease/oil arrestor/gross pollutant trap
      provided on site prior to being permitted to discharge into Council’s drainage system.
      All other clean stormwater, such as roof water, can be collected on site and discharged through
      a single underground drain line directly into the existing drainage system, bypassing the
      grease/oil arrestor/gross pollutant trap.
      To this end, a detailed maintenance plan shall be prepared for the proposed grease/oil
      arrestors/gross pollutant trap, which shall be submitted to the Council for approval prior to
      obtaining a Development Permit for Operational Works.
      The approved maintenance plan shall be incorporated in the Community Management Scheme
      for the development and a copy of this shall be provided for Council’s records prior to
      commencement of the approved use.
      A Development Permit for Building Works shall not be granted until a Development Permit for
      Operational Works has been issued in regard to the drainage scheme.
33.   All site stormwater drainage shall be by means of a gravity system.
Earthworks
34.   All earthworks (filling or excavation) required on site shall be carried out in accordance with
      Council’s Planning Scheme Policy PSP5 – Engineering Design Standards. Filling on the site
      shall not cause any additional ponding of water on any adjoining lands or the blockage of, or
      interference with, any natural watercourses.
35.   Any imported fill to the site may only be from a site licensed with The Environmental Protection
      Agency or from a site for which a Development Permit for Operational Works has been issued
      approving the export of fill.


                                                                                         Page 6 of 17

Page 7

                                                                                              2010/811



36.   Earthworks carried out on site shall not affect the structural integrity of any of the existing fences
      or structures that border the development site. Fences that are affected shall be replaced prior
      to the Building Certifier issuing the Certificate of Classification. In this regard any fences to be
      replaced shall be clearly shown on the plans submitted for Operational Works approval.
Erosion and Sediment Control
37.   Any person acting on this permit shall prevent erosion and sediment export from leaving the
      site. Site control measures such as silt fencing, controlled gravel access to the site and
      controlled disposal of waste, will be necessary.
      In this regard plans detailing the methods of controlling erosion and sediment are required to be
      submitted to the Council for approval prior to obtaining a Development Permit for Operational
      Works.
General Engineering Requirements
38.   A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
      specifications for all engineering works that will become Council infrastructure, which shall be
      submitted in conjunction with an application for a Development Permit for Operational Works.
      In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be
      submitted in conjunction with any application for Operational Works.
39.   Digital detailed designs including drawings, calculations, specifications and a schedule of works
      shall be submitted with any application for a Development Permit for Operational Works in
      respect of roadworks and stormwater drainage works. The design shall be in accordance with
      Council’s Planning Scheme Policy PSP05 – Engineering Design Standards – Roads, Drainage
      and Earthworks. To avoid conflict with underground pipes or services, all existing and proposed
      services required by the development shall be shown on the plans.
40.   To facilitate production of As Constructed drawings it is suggested that all design drawings are
      submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the
      use of ADAC are available at www.adac.com.au).
41.   Any damage caused to any public utility during the course of construction shall be repaired to
      Council’s standards and at no cost to Council.
42.   Any alteration of any public utility or other facilities necessitated by the development of the land
      or associated construction works external to the site shall be at no cost to Council.
43.   The transportation of all materials to and from the site shall be undertaken in a manner such
      that no particle matter escapes onto a public road. All vehicles carrying materials either to or
      from the site shall be covered to prevent materials including dust being windblown from the
      vehicle.
44.   As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
      for design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and
      type of all services and structures. All of which shall be submitted to Council for checking and
      for Council’s records.
      The data must fully detail levels for all engineering works including but not limited to drainage
      structures, finished ground levels and pavement surface levels. The data shall be submitted in
      the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC
      are available at www.adac.com.au). Approval of works shall not be granted until all As
      Constructed information has been supplied and accepted by Council.
Unity Water
45.   Reticulated water supply and sewerage must be provided to the development.
46.   Separate 25mm PE water services must be installed to a common lot boundary with
      independent meters installed outside the boundary of the lot in accordance with Sunshine Coast
      water standard drawing SCW 361. Meters must be “Elster” PSM 50100/39 (dual check).
47.   The sewer inspection opening must be located a minimum of 1.0 metre from any structure and
      be raised to the finished surface level of the site.

                                                                                              Page 7 of 17

Page 8

                                                                                            2010/811



48.   Storm water retention systems and gross pollutant traps must maintain a minimum clearance of
      1.5 metres from Council water supply and sewerage infrastructure.
49.   Landscape planting within 1.5 metres of Council sewerage infrastructure must be Council
      approved varieties and low growing when mature.
50.   Construction works undertaken in the vicinity of Council water supply or sewerage infrastructure
      must not adversely affect the integrity of the infrastructure. All costs associated with repair,
      replacement or alteration of infrastructure must be met by the applicant.
5     REFERRAL AGENCY CONDITIONS

The referral agencies applicable to this application are:
 Reason for             Relevant             Referral         Referral    Agency Address
 Referral               Regulation           Type             Agency
 Material change of     Sustainable          Concurrence      DERM        Department of Environment and
 use - Contaminated     Planning                                          Resource Management
 land (unexploded       Regulation 2009 -                                 Ecoaccess Customer Service Unit
 ordnance)              Schedule 7, table                                 PO Box 15155
                        3, item 11                                        CITY EAST QLD 4002

A copy of any referral agency conditions is attached.

6     APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following table:

 Plan / Document No.      Issue.   Plan / Document Name                                    Date
 0912 - CD 1.01           P6       Site Plan Ground Floor – Middap Ditchfield Pty Ltd      2 June 2010
 0912 - CD 0.04           P2       Easements – Middap Ditchfield Pty Ltd                   2 June 2010
 0912 - CD 3.01           P5       Site 22 Ground Floor Plan – Middap Ditchfield Pty Ltd   2 June 2010
 0912 - CD 3.02           P5       Site 22 First Floor Plan – Middap Ditchfield Pty Ltd    2 June 2010
 0912 - CD 3.03           P3       Site 22 Roof Plan – Middap Ditchfield Pty Ltd           2 June 2010
 0912 - CD 4.01           P3       East Elevation – Middap Ditchfield Pty Ltd              2 June 2010
 0912 - CD 4.02           P3       West Elevation – Middap Ditchfield Pty Ltd              2 June 2010
 0912 - CD 4.03           P3       South & North Elevation – Middap Ditchfield Pty Ltd     2 June 2010

7     ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of approval:
General
1.    Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if
      the cost of operational works exceeds $80,000, then a portable long service leave levy is
      required to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight the
      approved form issued by the Building and Construction Industry (Portable Long Service Leave)
      Authority that confirms that the requirements of the Act have been satisfied. A statutory
      declaration outlining the cost of the operational works must be submitted to Council with the
      lodgement of any application for operational works over the site.
2.    The development should be undertaken in a manner that causes no detrimental effect upon the
      amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-borne
      hazards, atmospheric pollutants (including dust or odours) nuisance or any other emissions in
      accordance with the nuisance provisions of the Environmental Protection Regulation 1998 or
      Council’s Local Law No. 12 – Control of Nuisances.


                                                                                           Page 8 of 17

Page 9

                                                                                              2010/811



3.    In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud, paint,
      cement, concrete, builder’s waste or rubbish should not be permitted to enter or be placed
      where it could reasonably be expected to move into a roadside gutter, storm water drain or a
      watercourse. On the spot fines apply for such offences.
4.    The applicant is advised that a Compliance Permit for all plumbing and drainage works within
      the boundaries of the development site shall be obtained from Council’s Plumbing Services
      Section prior to obtaining a Development Permit for Building Works.
5.    It is recommended that applications for Operational Works for permit 2010/0811 on Lot 84
      M11112 and permit 2010/0812 on Lot 85 M 11112 should be combined.
Water & Sewerage
6.    Connection to Council live water mains must be undertaken by Council at the applicants cost .
7.    Water meters must be located on alternative boundaries to power boxes.
8.    Water meters approved for use in the Sunshine Coast region may be purchased direct from
      “Elster” and installed by the developer, or Council can provide the meters and undertake the
      works. Meters must be “Elster” PSM 50100/39 (dual check). Council's quotation for the works
      will be prepared upon request
Infrastructure Contributions and Infrastructure Charge
9.    An advice notice outlining the estimated infrastructure contributions payable and the basis for
      their calculation under the current Planning Scheme Policies and Council Policies is attached
      with this Development Permit.
10.   The applicant is informed that this development permit will trigger an Infrastructure Charge in
      accordance with the Coastal Major Road Network Infrastructure Charges Plan for the estimated
      amount of $4,174.00 and is subject to variations in the Consumer Price Index, All Groups
      Brisbane from March 2010 until the date of payment. An Infrastructure Charge Notice will be
      issued in accordance with Chapter 8 of the Sustainable Planning Act 2009.
11.   Please        contact       Council's     Infrastructure   Charges       Officer     (email:
      [email protected]) a minimum of 5 business days prior to payment of the
      infrastructure contributions and/or charge notice so a payment advice detailing the amounts
      applicable at the time of payment may be issued to accompany the payment.
12.   Payment of infrastructure contributions and/or infrastructure charge notices will not be accepted
      by credit card transaction.
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not harm
Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act
can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage
or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.

8     PROPERTY NOTES

Not applicable.

9     PRELIMINARY APPROVAL OVERRIDING SCHEME

Not applicable.

                                                                                              Page 9 of 17

Page 10

                                                                                          2010/811



10     FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit required             Subject of the required Development Permit

 Development Permit                              Operational Works for Access and Carparking,
                                                 Stormwater Drainage, Frontage Works, Landscaping,
                                                 and Erosion & Sediment Control
 Development Permit                              All Building Works

11     SELF ASSESSABLE CODES
Not applicable.

12     SUBMISSIONS

Not applicable.

13     REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable.

14     RIGHTS OF APPEAL
You have continuing appeal rights in respect of Council’s decision on your application. Refer Section
4.1.27. of the Integrated Planning Act 1997.

15     OTHER DETAILS
Should you wish to obtain more information about Council’s decision, electronic copies of Council’s
decision are available on line at www.sunshinecoast.qld.gov.au, or at Council Offices.


Decision Notice History
12 July 2010                       Original Decision Notice.
25 October 2010 -                  Negotiated Decision Notice with
                                   amendments to Conditions 6 and 15

Yours faithfully,




Tracy Jones
Senior Development Planner



Enc:    Appeal Rights
        Referral Agency Response




c.c:    Department of Environment and Resource Management
        Ecoaccess Customer Service Unit
        PO Box 15155
        CITY EAST QLD 4002

c.c     Altum Constructions
        PO Box 2
        PEREGIAN BEACH QLD 4573
                                                                                        Page 10 of 17

Page 11

                                            2010/811




Referral Agency Conditions
SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING
REGULATION 2009




                                          Page 11 of 17

Page 12

  2010/811




Page 12 of 17


[OCR of page images]
2010/3811

 

BS
.
_
Notice
Concurrence Agency Response

3. General advice to assessment manager

_ Pursuant to sections 334 and 363 of the Act, a copy of a decision notice or negotiated decision notice issued
by the assessment manager must be forwarded to DERM as a referral agency for the relevant application at:

Permit and Licence Management

Implementation and Support Unit

Department of Environment and Resource Management
GPO Box 2454, Brisbane QLD 4001

and an electronic copy to [email protected] State’s Native Title Work Procedures provide that responsibility for assessment of native title issues for
an IDAS application rests with the assessment manager. Therefore, DERM as a referral agency for the

 

relevant application has not provided notification to.native title parties. - + . : no
Wen ake y ene: ay Ue eae a naa aay sere RET tt as ale . :
4. Additional information for applicants .

Contaminated Land: It is a requirement of the Environmental Protection Act 1994 that if an owner or
occupier of land becomes aware of a Notifiable Activity (as defined in Schedule 3 and Schedule 4 of the
Enviranmental Protection Act 1994) is being carried out on the land, or that the land has been, or is being,
contaminated by a hazardous contaminant, the owner or occupier must, within 22 business days after

. becoming so aware, give written notice to DERM.

5, Reasons for inclusion of development condition/s or refusal
{in accordance with section 289 of the Sustainable Planning Act 2009 and section 278 of the Acts interpretation Act
1954, a concurrence response must include reasons for a refusal or for the inclusion of development conditions.)

The site (the subject lot/s) is part of an area of land within which the Department of Defence (Defence) has
. assessed a ‘substantial’ risk of residual UXO contamination exists. Visit the Defence website

htto://www.defence.gov.au/uxo/ for details.

Defence advises that development or land use rezoning proposals for land within a ‘substantial' zone should
only praceed following the conduct of UXO investigation and clearance activities. Defence maintains a list of
commercial UXO investigation and remedial search contractors that it accredits to carry out this work.

Defence also recommends that owners or occupiers of potentially affected land and workers and contractors
employed on the land need to be aware of the procedure if a suspect object is found.

As DERM has no record of the site being further investigated or remediated, it is considered that there
remaing a possibility of UXO being found onit. , . +
7

  

 
 

 

 

Ranald Scott .
Delegate, Chief Executive administering . Enquiries:
the Sustainable Planning Act 2009 o Ranald Scott
Department of Environment and Resource Management DERM
(DERM) . Level 1, The Esplanade, Maroochydore QLD
. PO Box 168, Cotton Tree, QLD 4558
30 June 2010 Phone: 075459 6129 Fax: 07 5443 9927
+ so. : ‘Email: [email protected]
2Attachment::Conditions Bee RRA TAMER. 5 sk Re
4 aA CaO | ' ee ee ED toe Bale lt
~ Page’2 of 4 «091217 Department of Environment and Resource Management

Page 12 of 17

Page 13

  2010/811




Page 13 of 17


[OCR of page images]
2010/3811

 

 

 

Notice———.
Concurrence Agency Response

CONDITIONS

The foltowing concurrence agency conditions are to be attached to any approval:

41 Prior to the commencement of any development-related excavation, earthworks or soil disturbance,
that part of the site to be so worked is to be subjected to investigation and, where Necessary,
appropriate remedial action.

2 Any person employed to work on any part of the site where Condition 1 has not been satisfied is to
be forewarned in writing by the applicant. .

This warning-is to explain that information available to DERM indicates a potential for residual UXO

exists on the site‘and work should preceed-with-due caution: ‘Itis-to-state-the precedure-to be -
followed by any person finding an object suspected of being explosive ordnance or component
thereof:

Do not disturb the object.

Take action, where appropriate, to prevent it being disturbed by another person.
Note its approximate dimensions and general appearance.

Note the route to its location.

Advise the Police as soon as possible.

eeeee

3 Following investigation and any remedial action taken to-satisfy Condition 1 above, the applicant is to
submit a report, prepared in accordance with current guidelines, to DERM for assessment. DERM is
to Subsequently advise the Sunshine Coast Regional Council and the applicant of its assessment i in
regard to Condition 1 being satisfied.

4 Prior to Condition 3 being satisfied, no excavated gravel, rock, sand or soil is to be removed from the
site without written DERM approval.

5 The applicant is to advise the owner and any occupier of the site of the above responsibilities.

General comments or advice about applications concerning land potentially affected by UXO

Appricants may. contact DERM’s Project Manager (UXO) or visit Defence’s website

http://Awww.defence.gov.au/uxo/ for the details of current UXO investigation and remedial search contractors.
DERM accepts reports based on investigative and remedial work carried out by these contractors.
Investigation and remedial action to satisfy Condition 1 typically involves sampling/search programs with
detection equipment unless the use of such equipment is:

e considered unwarranted by a UXO contractor due to the extent of any prior excavation or
earthworks or, conversely, of any filling proposed as part of the development program; or

* prevented or made impracticable by the presence of a structure, stockpile, natural barrier or metal
waste.

In the latter case, alternative action may be appropriate to minimise the risk in the first instance. For
example, where the risk of exposure to any UXO that may exist is reduced by the presence of a structure or
natural barrier, issuance of the standard UXO warning (see Condition 2) may suffice while the structure,
-« Stockpile or barrier.remains in-place.-Where.a:structure is.to:be removed or reduced as part of the
srdevelopment program, protective'precautions, commensurate with any greater risk to which workers might

 

Page 3 of 4 + 091217 . Department of Environment and Resource Management

Page 13 of 17

Page 14

  2010/811




Page 14 of 17


[OCR of page images]
2010/3811

 

*
oN
Notice
: Concurrence Agency Response

_ then be exposed, may need to be considered. Progressive assessment will be necessary where, such
circumstances exist. Unless, at the completion of preliminary works, there is evidence then available to the
UXO contractor that any residual risk is negligible, the use of detection equipment will typically be required
to confirm the site's status.

Where investigation, along with any subsequent remedial action and assessment, is to be implemented by

stages to satisfy Condition 1 and 3, a preliminary investigation report should be submitted by the applicant to

DERM along with a management plan for the proposed work. Staged investigation/remediation is most likely

to be applicable where development of smaller, built-on lots (which can present circumstances such as those -
discussed above) or broadhectare sites is proposed. In such cases, DERM’s assessment of the report and \
advice to Council in regard to approval of the development will be dependent on agreement with the

management plan.

Where Condition 1 is tobe satisfied by a whole lot or broadhectare development stage being subjected to
investigation and any necessary remedial action, DERM, based on the subsequent investigation/remediation
report's findings and recommendation/s, may reassess the lot, or that portion comprising the development
stage, as being remediated or not needing remediation, and advise the applicant and Council accordingly.
Otherwise, any balance of land that has not been further investigated will retain the risk assessment made by
Defence and DERM's Area Management Advice will continue to apply. This is unless evidence obtained from
the investigated part/s can be used to refute Defence's assessment in regard to all or part of the balance. In
the latter case, DERM may reassess all of the balance or the applicable part/s as being unaffected by UXO.

END OF CONDITIONS

yo
tags
ee

Page 4 of 4091217 Department of Environment and Resource Management,

Page 14 of 17

Page 15

                                                                                                       2010/811




                                                   Appeal Rights
                                                  SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING
                                                  REGULATION 2009




The following is an extract from the Sustainable                        (ii) the length of a period mentioned in
Planning Act 2009 (Chapter 6).                                               section 341 for the approval.
                                                             (3)    However, a submitter may not appeal if the
MATERIAL CHANGE OF USE, RECONFIGURING A                             submitter—
LOT & OPERATIONAL WORKS
                                                                    (a) withdraws the submission before the
Division 8 - Appeals to court relating to development                   application is decided; or
applications                                                        (b) has given the assessment manager a
461     Appeals by applicants                                           notice under section 339(1)(b)(ii).
(1)     An applicant for a development application           (4)    The appeal must be started within 20 business
        may appeal to the court against any of the                  days (the submitter’s appeal period) after
        following-                                                  the decision notice or negotiated decision
                                                                    notice is given to the submitter.
        (a) the refusal, or the refusal in part, of a
            development application;                         463   Additional and extended appeal rights for
                                                                   submitters for particular development
        (b) any condition of a development approval,               applications
            another matter stated in a development
            approval and the identification or inclusion     (1)    This section applies to a development
            of a code under section 242                             application to which chapter 9, part 7
                                                                    applies.
        (c) the decision to give a preliminary approval
            when a development permit was applied            (2)    A submitter of a properly made submission for
            for;                                                    the application may appeal to the court about
                                                                    a referral agency’s response made by a
        (d) the length of a period mentioned in section             prescribed concurrence agency for the
            341;;                                                   application.
        (e) a deemed refusal of the development              (3)    However, the submitter may only appeal
            application.                                            against a referral agency’s response to the
(2)     An appeal under subsection (1)(a), (b), (c) or              extent it relates to—
        (d) must be started within 20 business days                 (a) if the prescribed concurrence agency is the
        (the applicant’s appeal period) after—                          chief    executive       (environment)—
        (a) if a decision notice or negotiated decision                 development for an aquacultural ERA; or
            notice is given—the day the decision                    (b) if the prescribed concurrence agency is the
            notice or negotiated decision notice is                     chief executive (fisheries)—development
            given to the applicant; or                                  that is—
        (b) otherwise—the day a decision notice was                     (i)    a material change of use of premises
            required to be given to the applicant.                             for aquaculture; or
(3)     An appeal under subsection (1)(e) may be                        (ii) operational work that is the removal,
        started at any time after the last day a decision                      damage or destruction of a marine
        on the matter should have been made.                                   plant
462     Appeals by submitters - general                      (4)    Despite section 462(1), the submitter may
(1)     A submitter for a development application may               appeal against the following matters for the
        appeal to the court only against-                           application even if the matters relate to code
                                                                    assessment—
        (a) the part of the approval relating to the
            assessment manager’s decision about any                 (a) a decision about a matter mentioned in
            part of the application requiring impact                    section 462(2) if it is a decision of the chief
            assessment under section 314; or                            executive (fisheries);
        (b) the part of the approval relating to the                (b) a referral agency’s response mentioned in
            assessment manager’s decision under                          subsection (2).
            section 327.                                     464   Appeals by advice agency submitters
(2)     To the extent an appeal may be made under            (1)    Subsection (2) applies if an advice agency, in
        subsection (1), the appeal may be against 1 or              its response for an application, told the
        more of the following—                                      assessment manager to treat the response as
        (a) the giving of a development approval;                   a properly made submission.
        (b) any provision of the approval including—         (2)    The advice agency may, within the limits of its
                                                                    jurisdiction, appeal to the court about—
            (i)     a condition of, or lack of condition
                    for, the approval; or


                                                                                                     Page 15 of 17

Page 16

                                                                                             2010/811



      (a) any part of the approval relating to the       467    Appeals about changing or cancelling
         assessment manager’s decision about any                conditions     imposed       by     assessment
         part of the application requiring impact               manager or concurrence agency
         assessment under section 314; or                (1)    A person to whom a notice under section
      (b) any part of the approval relating to the              378(9)(b) giving a decision to change or
         assessment manager’s decision under                    cancel a condition of a development approval
         section 327                                            has been given may appeal to the court
(3)   The appeal must be started within 20 business             against the decision in the notice.
      days after the day the decision notice or          (2)    The appeal must be started within 20 business
      negotiated decision notice is given to the                days after the day the notice of the decision is
      advice agency as a submitter.                             given to the person.
(4)   However, if the advice agency has given the        For Building Works Only
      assessment manager a notice under section          532    Appeals by applicants
      339(1)(b)(ii), the advice agency may not
      appeal the decision.                               (1)    If—
465   Appeals about decisions relating to                       (a) a person has been given, or is entitled to
      extensions for approvals                                     be given—
(1)   For a development approval given for a                        a.      an information notice under the
      development application, a person to whom a                           Building Act about a decision
      notice is given under section 389, other than a                       other than a decision under that
      notice for a decision under section 386(2),                           Act made by the Queensland
      may appeal to the court against the decision in                       Building Services Authority; or
      the notice.                                                   b.      an information notice under the
(2)   The appeal must be started within 20 business                         Plumbing and Drainage Act
      days after the day the notice of the decision is                      2002 about a decision under
      given to the person.                                                  part 4 or 5 of that Act; or
(3)   Also, a person who has made a request under               (b) a person—
      section 383 may appeal to the court against a                 a.        was an applicant for a building
      deemed refusal of the request                                           development approval; and r
(4)   An appeal under subsection (3) may be                         b.        is dissatisfied with a decision
      started at any time after the last day the                              under the Building Act by a
      decision on the matter should have been                                 building certifier or referral
      made.                                                                   agency about inspection of
                                                                              building work the subject of the
466   Appeals about decisions relating to
                                                                              approval; the person may
      permissible changes)
                                                                              appeal against the decision to a
(1)   For a development approval given for a                                  building     and    development
      development application, the following persons                          committee.
      may appeal to the court against a decision on
                                                         (2)    An appeal under subsection (1) must be
      a request to make a permissible change to the
                                                                started within 20 business days after the day
      approval—
                                                                the person is given notice of the decision.
      (a) if the responsible entity for making the       (3)    If—
         change is the assessment manager for the
         application—                                           (a) under the Building Act, a person makes
                                                                    an application other than a building
         (i)    the person who made the request; or                 development application to a local
         (ii)   an entity that gave a notice under                  government; and
                section 373 or a pre-request                    (b) the period required under that Act for the
                response notice about the request
                                                                    local     government      to  decide   the
      (b) if the responsible entity for making the                  application (the decision period) has
          change is a concurrence agency for the                    passed; and
          application—the person who made the                   (c) the local government has not decided the
          request..                                                 application; the person may appeal to a
(2)   The appeal must be started within 20 business                 building and development committee
      days after the day the person is given notice of              against the lack of the decision and for
      the decision on the request under section 376.                the committee to decide the application
(3)   Also, a person who has made a request under                   as if it were the local government.
      section 369 may appeal to the court against a      (4)    An appeal under subsection (3) must be
      deemed refusal of the request.                            started within 20 business days after the end
(4)   An appeal under subsection (3) may be                     of the decision period..
      started at any time after the last day the
      decision on the matter should have been
      made.


                                                                                             16 of 17

Page 17

2010/811




17 of 17


[OCR of page images]
2010/8114

 

17 of 17

Used in these records

About this file

File size
295 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED Negotiated Decision Notice - 010.2010.00000811.001 [As Published].pdf · 295 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗