SPECIAL MEETING MINUTES 31 AUGUST 2020
29. Stormwater runoff from the development must be controlled and disposed
of into a lawful point of discharge and in a manner that does not cause
scour or damage to the subject site or any adjoining property including
Council’s drainage system.
30. Any drainage line or stormwater outlet located within the adjoining
vegetation covenant or easement area must be aligned to minimise the
impacts on existing vegetation with the final alignment determined on-site
in agreement with Council’s delegate.
31. Streetscape bioretention devices are to be detailed with the Operational
Works application and are to specifically address the following:
a. are designed generally in accordance with the Bioretention Technical
Design Guidelines,
b. are designed generally in accordance with IPWEQA Standard
Drawing No. WSUD-001 are provided with a free-draining outlet from
the sub-soil drainage system,
c. are designed with offsets to underground services in accordance with
utility services provider’s requirements,
d. allow for the safe movement of pedestrians along the road verge
either through provision of a path behind the device or pedestrian
refuge in the case of no path being provided,
e. have stable batter slopes which are designed to avoid the need for
safety fencing or bollards, or incorporate grates,
f. have plantings setback from the road pavement a sufficient distance
to not affect the road pavement during operation or re-setting,
g. are designed with a connection from the kerb to the filter media
surface which is sufficiently robust and not prone to blockage.
32. All stormwater quality treatment devices contained in private lots must be
maintained in accordance with the Water by Design (2009) Maintaining
Vegetated Stormwater Assets (Version 1). The approved Operational
Works drawings for the stormwater quality treatment system and detailed
life cycle costing of the system must be attached as an addendum to this
document. Records of all maintenance activities undertaken must be kept
and made available to Council upon request.
Electricity and Telecommunication Services
33. Underground reticulated electricity and telecommunication services must
be provided to each lot in accordance with an approval for Operational
Works and the standards and requirements of the relevant service provider.
34. Unless otherwise stipulated by telecommunications legislation at the time
of construction, the development must be provided with all necessary
conduits, pits and pipes to accommodate the future connection of optic fibre
technology telecommunications.
35. Certification must be submitted to Council from all relevant service
providers which certifies that the development has met the requirements of
this Decision Notice and all applicable legislation at the time of
construction.
Page 9 of 15
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.