SPECIAL MEETING MINUTES 31 AUGUST 2020
Car Parking
23. Parking located along the emergency access route within Lots 11-15 must
be limited to the individual lot. The easement documents for the emergency
access route must include sufficient detail to limit the movement of vehicles
and parking to the individual lot and clear of the emergency access route.
Pedestrian and Bicycle Facilities
24. Pedestrian and bicycle facilities must be provided for the development. The
works must be undertaken in accordance with an Operational Works
approval and must include in particular:
a. the on-road bicycle lanes as shown on the approved plans,
b. the footpath network as shown on the approved plans,
c. the footpath within proposed Lots 3 and 4, being Easement Al and
Easement AO, must be constructed as part of the subsequent
development of Lots 3 and 4. The pathway is to extend from the
Hofmann Drive frontage to the common boundary between Lots 3
and 24. The works must be undertaken in accordance with an
operational works approval and include a 3m wide sealed surface,
drainage d suitable lighting for pedestrian safety (CPTED). Despite
condition 1, the timing for the construction of the pathway is at the
time of the subsequent development of Lots 3 and 4,
d. the footpath on the northern side of Hofmann Drive must be extended
from the crossing point adjacent to Lot 4 to the north west for the full
frontage of Covenant J,
e. all footpaths and associated infrastructure located within private
property must be maintained by the property owner.
This condition is imposed pursuant to s145 of the Planning Act 2016 being
non-trunk infrastructure.
Stormwater Drainage
25. All stormwater drainage infrastructure must be located outside of the open
space covenants unless approved as part of an Operational Works
application.
26. As part of any future Material Change of Use application for proposed Lot
4, 5 or 6, a Stormwater Management Plan is to be provided and stormwater
quality treatment devices are to be incorporated into the site layout such
that the pollutant load reduction targets specified in Appendix 2, Table B of
the State Planning Policy 2017 are achieved (refer property note).
27. A stormwater quality treatment system must be provided for the
development. The works must be undertaken in accordance with an
Operational Works approval and the Bioretention Technical Design
Guidelines (Water by Design, 2012), and must include in particular
stormwater quality treatment devices of a size and location generally in
accordance with those shown in the Site-based Stormwater Management
Plan – Version 5, prepared by Barlow Shelley Consulting Engineers Pty
Ltd, dated 2nd December 2019. The bio retention devices are required to
treat runoff from the bushfire access and carparks within Lots 12-15.
28. The site must be provided with a stormwater drainage system connecting
to a lawful point of discharge. The works must be undertaken in
accordance with an Operational Works approval in compliance with the
relevant sections of Queensland Urban Drainage Manual.
Page 8 of 15
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.