Decision Notice - OPW23 0168 [As Published]
4. ASSESSMENT MANAGER CONDITIONS
APPROVED PLANS
1. Development undertaken in accordance with this approval must generally comply with the
approved plans of development. The approved plans are listed in the following table unless
otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
32038-OW3.1 A Earthworks Plan 20/12/2023
32038-OW1.1 A Stormwater Management Plan 20/12/2023
The following plans require amendment.
Plan No. Rev. Plan/Document Name Date
21-33 Link 49 Proposed Landscaping Plan, prepared by, JMF 28/06/2022
Design
Amendments The landscape plans must be resubmitted prior to a prestart meeting and
incorporate the following:
a. Remove the reference to fencing along the Edward Street
frontage and show the fence location in accordance with the
MCU approved plans.
b. Remove underground water tanks from under the garden beds
and relocate under the driveway.
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 5 February 2026, unless an application to extend the currency period
is approved by Council.
PRIOR TO COMMENCEMENT OF WORKS
3. Submit amended plans to Council as described in the List of plans requiring amendments.
Plans must be submitted and approved prior to the pre-start meeting.
4. Tree protection fencing must be installed under the supervision of the Project Arborist. (Refer
to Retention of Existing Trees Conditions).
5. All necessary approvals from external service providers (eg Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
6. Copies of the approved plans, duly signed by the consultant Registered Professional
Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer
Construction at the “pre start” meeting.
7. A condition report of the drainage system must be completed for agreement at the prestart
meeting. The condition report is to include a CCTV inspection of the existing pipe and must
include at least 10m upstream and downstream of all works.
8. A condition report including photographs of the frontage of the site must be completed and
submitted to council at the prestart meeting.
9. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
Page 2 of 11
Document Set ID: 22803369
Version: 4, Version Date: 08/02/2024