Decision Notice - OPW23 0168 [As Published]
10. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Landscape works;
11. A preliminary Construction Management Plan must be submitted with the Operational Works
application and must address the following:
a. Appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
Devices (MUTCD)
b. Provision for safe pedestrian and vehicle access across the frontage of the site both
during daily construction and after daily construction has ceased.
12. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
13. Any conflict between the development and an existing or proposed service must be referred
to the relevant service authority for determination prior to commencement of works.
Landscaping Works
14. Landscape works must be supervised, undertaken and certified by qualified persons*. All
works must be completed in accordance with this Decision Notice and must include in
particular:
a. The works generally shown on the Approved Plans except where varied by the
conditions of this approval. The landscape plans must be resubmitted prior to a prestart
meeting.
DURING CONSTRUCTION
Engineering
15. The developer must meet any costs to repair damage to any Council asset during
construction, where damage is a result of the development works. Damage to assets must
be repaired immediately where it creates a hazard to the community. In circumstances where
the damage does not create a hazard to the community, it must be repaired immediately on
completion of the works associated with the development.
16. All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
who is independent of the Developer and Principal Contractor, and they must certify that all
works conform to the Operational Works permit. Where municipal works are involved, such
confirmation must be submitted for the respective hold points prior to any site inspection by
Council Officers.
17. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice
b. The relevant conditions of the higher order Material Change of Use approval viz.
MCU22/0111 to which this approval relates
c. All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
specifications and guidelines
d. The latest version of the Healthy Waterways document “Water Sensitive Urban Design
Technical Design Guidelines for South East Queensland” for all water quality devices
to be constructed on site
Page 3 of 11
Document Set ID: 22803369
Version: 4, Version Date: 08/02/2024