Civil Engineering Onsite Effluent Assessment · MCU13/0064
In accordance with the original Site and Soil Evaluation Report (ref no. 2771-02)
completed by FPE on the 20th June 2007, the AWTS is to have a peak design
capacity of not less than 2,475L/day (13 equivalent persons (EP)). Based on
information supplied by the existing service agent (H2Gold), the AWTS currently
has the peak design capacity of up to 2,700L/day (14 EP) and wet weather storage
capacity of 10,000L. The existing AWTS also has the ability to expand the peak
design capacity of the system through the modification of the internal pump
timing. This is considered to be satisfactory. Photo Plate 1 contained in
Attachment 1 of this correspondence identifies the existing STP.
Treated effluent is currently irrigated via a subsurface irrigation system within
two (2) designated effluent disposal areas. The disposal areas were originally
designed for 495m2 however a total area of 540m2 of raised garden beds was
installed for conservative purposes. The existing raised garden beds have the
capacity to handle a daily irrigation rate of 2,700L based on Table M1 of
AS1547:2012. At the time of the inspection, the effluent disposal areas appeared
to be in good condition, with consistent ground cover. Photo Plate 2 contained in
Attachment 1 of this correspondence identifies the existing land application area.
Wastewater Hydraulic Loading
In accordance with the proposed change in use, the accommodation facilities
located at Makepeace Island will have the capacity to cater for a total of twenty
(20) guests, located in a series of free standing buildings. In addition to the guest
accommodation facilities, a total of five (5) staff members service the island, not
including cleaning staff provided by an external company:
Two (2) staff members (traditionally Chef and Hostess) are permanently
accommodated on-site within the caretaker’s residence.
Two (2) staff members (traditionally Skipper and Maintenance) access the
island between the hours of 7am to 10pm. However, during high
occupancy, the two (2) staff members can also be accommodated onsite.
One (1) additional staff member (traditionally General Manager) accesses
the island between the hours of 7am to 10pm.
Two (2) cleaning staff members are provided by an external company and
access the island for a period of approximately six (6) hours to undertake
pre and post guest cleaning.
The hydraulic loading associated with the guest and staff accommodation
facilities can be most reliably calculated using Chapter 5 Table A of DEHP
(formerly DNR&M) Planning Guidelines for Water Supply and Sewerage, as
follows:
p: 07 5450 2688 e: [email protected] PO Box 1250, Buddina Q 4575
f: 07 5450 2686 www.future-plus.com.au ABN 23 658 506 336
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Civil Engineering Onsite Effluent AssessmentRelated documentApplication case desk ↗
About this file
- File size
- 1.1 MB (small file)
- File type
No other editions are linked here.