Attachment 6 - Stormwater Management Plan and Engineering Response. · MCU23/0078
Plans and drawings: the text below has words only, no drawings.
Very large file (32.8 MB): may take a few minutes to open.
Original PDF page 16, section 1. The text section number identifies this passage in the reader.
Table 16: XP Storm Developed Unmitigated Peak Flow Results – Lot 7 (South) (m3/sec)
ARI & AEP
Storm Duration
1 Years 2 Years 5 Years 10 Years 20 Years 50 Years 100 Years
(min)
63% 39% 18% 10% 5% 2% 1%
20 0.143 0.161 0.218 0.255 0.290 0.308 0.339
25 0.138 0.156 0.212 0.254 0.292 0.306 0.339
30 0.126 0.143 0.195 0.234 0.270 0.287 0.319
45 0.115 0.130 0.179 0.211 0.242 0.266 0.299
60 0.121 0.138 0.196 0.237 0.277 0.304 0.339
90 0.105 0.121 0.176 0.210 0.244 0.253 0.283
120 0.102 0.117 0.171 0.207 0.242 0.249 0.280
180 0.065 0.075 0.111 0.134 0.157 0.167 0.189
Critical 0.143 0.161 0.218 0.255 0.292 0.308 0.339
Critical Even (Min) 20 20 20 20 25 20 20
Discharge hydrographs for the existing model have been included in Appendix F.
4.2.6 Detention Basin Design
For the developed mitigated scenario, storage nodes representing the proposed detention basins were included in the
model. Flows from all three development catchments were routed to the assigned detention tanks for each catchment.
The storage node inputs were sourced based on in-ground tanks for all three catchments, as well as the proposed bio-
basins discussed in Section 5. The six detention tanks modelled for each of the three catchments are outlined in Table 17.
Table 17: XP Storm Developed Model Hydraulic Routing
Development Sub-Catchment Invert Elevation Internal Height Surface Area Approximate Volume
(RL) (m) (m2) (m3)
Lot 3 Detention Tank 5.50 2.5 800 2,000
Lot 3 Bio-Retention Basin 3.80 1.5 560 840
Lot 7 (North) Detention Tank 6.50 1.8 110 200
Lot 7 (North) Bio-Retention Basin 6.30 1.8 27 49
Lot 7 (South) Detention Tank 6.50 1.8 160 228
Lot 7 (South) Bio-Retention Basin 6.30 1.8 33 60
The outlets to each of the three detention tanks were modelled as per the below:
• Lot 3 Catchment:
o Detention Tank:
▪ Low-flow outlet: 150mm diameter orifice with invert at RL 5.50m;
▪ Mid-flow outlet: 300mm diameter orifice with invert at RL 6.90m;
▪ High-flow outlet: 525mm diameter orifice with invert at R: 6.90m; and
▪ High-flow weir: 10m long weir with crest height at RL 7.20m.
o Bio-Retention Basin:
▪ Low-flow outlet: 300mm diameter orifice with invert at RL 5.30m;
▪ Mid-flow outlet: 300mm diameter orifice with invert at RL 6.60m;
▪ High-flow outlet: 100mm diameter orifice with invert at R: 6.80m; and
▪ High-flow weir: 10m long weir with crest height at RL 7.65m.
www.bornhorstward.com.au Page 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 6 - Stormwater Management Plan and Engineering Response..pdfRelated documentApplication case desk ↗
About this file
- File size
- 32.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.