Attachment 6 - Stormwater Management Plan and Engineering Response. · MCU23/0078
Plans and drawings: the text below has words only, no drawings.
Very large file (32.8 MB): may take a few minutes to open.
Original PDF page 45, section 1. The text section number identifies this passage in the reader.
20/11/2023 + JOB No:-
INITIAL PEAK FLOW ESTIMATE
Written by BB 31/10/08
Updated by DJK 25/05/20
Job Number: 22159
Job Name: LOT 7 Southern Site - Noosa Civic Village Expansion
Designed: VN
Checked: SG IFD Location: Noosaville
TOTAL RUNOFF COEFF. EXISTING TIME OF CONCENTRATION DEVELOPED TIME OF CONCENTRATION
Sub Catchment Area (Ha) Fraction Impervious Runoff Coeficients Calculated C10 Std Inlet Time 5 Std Inlet Time 5
No. Existing Proposed Existing Proposed Existing Proposed Existing Proposed
SHEET FLOW
SHEET FLOW
1 0.338 0.338 0% 90% 0.60 0.88 Site Slope (%) 1.2 Site Slope (%) 0
2 0.000 0.000 0% 0% 0.00 0.00 Flow Length (m) 40 Flow Length (m) 0
3 0.000 0.000 0% 0% 0.00 0.00 Horton's "n" 0.16 Horton's "n" 0
4 0.000 0.000 0% 0% 0.00 0.00 Travel Time (min) 56.45 Travel Time (min) 0.00
5 0.000 0.000 0% 0% 0.00 0.00
0.338 0.338 0.60 0.88 Travel Length (m) 0 Travel Length (m) 200
CHANNEL/PI
CHANNEL/PI
PE FLOW
PE FLOW
Raw IFD data has been obtained from the Bureau of Meteorology (BOM) website. Fall (m) 0 Fall (m) 5.6
Travel Time (min) 0 Travel Time (min) 2
Multiplier 0 Multiplier 1
Travel Time (min) 0 Travel Time (min) 2
Total Time (Tc) 61.5 Total Time (Tc) 7.0
PEAK RUNOFF CALCULATIONS PEAK FLOWS FOR FREQUENT EVENTS
Rainfall Intensity (mm/hr) Coeficient of Runoff Peak Runoff Rates (m^3/s) ARI Event % of Q1 Peak discharge (m^/s)
AEP Event % ARI Event yr Existing Proposed Existing Proposed Existing Proposed yr Existing Proposed
63% 1 48 136 0.48 0.70 0.021 0.090 1mth 25% 0.005 0.023
39% 2 54 154 0.51 0.75 0.026 0.108 2mth 40% 0.009 0.036
18% 5 75 209 0.57 0.84 0.040 0.164 3mth 50% 0.011 0.045
10% 10 88 245 0.60 0.88 0.050 0.202 4mth 60% 0.013 0.054
5% 20 102 279 0.63 0.92 0.060 0.242 6mth 75% 0.016 0.068
2% 50 119 322 0.69 1.00 0.077 0.302 9mth 90% 0.019 0.081
1% 100 133 354 0.72 1.00 0.090 0.332 12mth 100% 0.021 0.090
^ 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 6 - Stormwater Management Plan and Engineering Response..pdfRelated documentApplication case desk ↗
About this file
- File size
- 32.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.