Attachment 6 - Stormwater Management Plan and Engineering Response. · MCU23/0078
Plans and drawings: the text below has words only, no drawings.
Very large file (32.8 MB): may take a few minutes to open.
Original PDF page 44, section 1. The text section number identifies this passage in the reader.
20/11/2023 + JOB No:-
INITIAL PEAK FLOW ESTIMATE
Written by BB 31/10/08
Updated by DJK 25/05/20
Job Number: 22159
Job Name: LOT 7 Northern Site- Noosa Civic Village Expansion
Designed: VN
Checked: SG IFD Location: Noosaville
TOTAL RUNOFF COEFF. EXISTING TIME OF CONCENTRATION DEVELOPED TIME OF CONCENTRATION
Sub Catchment Area (Ha) Fraction Impervious Runoff Coeficients Calculated C10 Std Inlet Time 0 Std Inlet Time 5
No. Existing Proposed Existing Proposed Existing Proposed Existing Proposed
SHEET FLOW
SHEET FLOW
1 0.249 0.249 0% 90% 0.60 0.88 Site Slope (%) 2.4 Site Slope (%) 0
2 0.000 0.000 0% 0% 0.00 0.00 Flow Length (m) 45 Flow Length (m) 0
3 0.000 0.000 0% 0% 0.00 0.00 Horton's "n" 0.16 Horton's "n" 0
4 0.000 0.000 0% 0% 0.00 0.00 Travel Time (min) 51.11 Travel Time (min) 0.00
5 0.000 0.000 0% 0% 0.00 0.00
0.2488 0.2488 0.60 0.88 Travel Length (m) 0 Travel Length (m) 0
CHANNEL/PI
CHANNEL/PI
PE FLOW
PE FLOW
Raw IFD data has been obtained from the Bureau of Meteorology (BOM) website. Fall (m) 0 Fall (m) 0
Travel Time (min) 0 Travel Time (min) 0
Multiplier 0 Multiplier 0
Travel Time (min) 0 Travel Time (min) 0
Total Time (Tc) 51.1 Total Time (Tc) 5.0
PEAK RUNOFF CALCULATIONS PEAK FLOWS FOR FREQUENT EVENTS
Rainfall Intensity (mm/hr) Coeficient of Runoff Peak Runoff Rates (m^3/s) ARI Event % of Q1 Peak discharge (m^/s)
AEP Event % ARI Event yr Existing Proposed Existing Proposed Existing Proposed yr Existing Proposed
63% 1 53 148 0.48 0.70 0.018 0.072 1mth 25% 0.004 0.018
39% 2 60 168 0.51 0.75 0.021 0.087 2mth 40% 0.007 0.029
18% 5 83 229 0.57 0.84 0.033 0.133 3mth 50% 0.009 0.036
10% 10 98 270 0.60 0.88 0.040 0.164 4mth 60% 0.011 0.043
5% 20 112 309 0.63 0.92 0.049 0.197 6mth 75% 0.013 0.054
2% 50 131 359 0.69 1.00 0.063 0.248 9mth 90% 0.016 0.065
1% 100 146 397 0.72 1.00 0.072 0.274 12mth 100% 0.018 0.072
^ 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 6 - Stormwater Management Plan and Engineering Response..pdfRelated documentApplication case desk ↗
About this file
- File size
- 32.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.