NOOSA COUNCIL IDAS Development Application Decision Notice                                                7 of 10


      CCTV inspection will be carried out by Council's CCTV contractor and arranged by Council following
      satisfactory completion of construction works. The developer will be responsible for the full cost of CCTV
      inspection, including any additional inspection necessary following defect identification and rectification.
      This charge is payable prior to commencement of works and will be determined on the unit rate basis
      current at the time of approval.
44.   All signage, including that for safety during construction shall be in accordance with the Manual of Uniform
      Traffic Control Devices and Main Roads Department Roadworks Signing Guide.

45.   As Constructed drawings in both hardcopy and digital format (ADAC) produced in GDA94 Zone 56
      coordinate value to the standards and requirements of the Assessment Manager are required for Council
      records. Such 'as constructed' drawings will be required prior to works being accepted "on maintenance",
      where applicable. Requirements for "as constructed" information are detailed in the current version of
      Council's Engineering Design Standards (Water & Sewerage) Manual.
      Release of plans of survey and/or acceptance of the works on-maintenance will not be considered until
      lodgement of satisfactory 'as constructed' records.
      Please note that bonding of outstanding works will not be considered by Council.
46.   Your company, is responsible for arranging all inspections and ensuring that all relevant details required
      by Council are supplied. The attached Water and Sewerage Inspection Report form is to be kept by you
      and presented to Council's Inspector at each stage of the development requiring a meeting or inspection.
      The Inspector will sign the form at each stage when conditions have been satisfied. The works will be
      accepted 'on maintenance' when this form, signed by the Inspector for each stage, is returned with a letter
      requesting that it go 'on maintenance'.

47.   It is Council policy that a maintenance bond be imposed on construction works during the maintenance
      period. The maintenance bond shall be 5% of the agreed value of the development obligations, or $1,500
      whichever is the greater amount. This bond must be lodged by (and shall only be accepted from) the
      Developer for the works.

48.   Construction work and other associated activities are permitted only during the hours of 7:00am and
      6:00pm Monday to Saturday. No work is permitted on Sundays or public holidays, except where extended
      hours are approved by the Assessment Manager or his nominee.

49.   Cut-ins to existing live sewer are to be performed by Approved Contractor. Noosa Council Works
      Inspector shall be present during any work on live sewer undertaken by contractor. An additional fee of
      $140.00 (included below) is required to cover costs associated with these live sewer works.

50.   Fees applicable to the above project are listed below:-
      Plan Examination                           $ 710.00
      Inspection Fee                             $ 710.00
      Checking as-constructed data               $ 442.50
      CCTV fee                                   $ 120.00
      Live sewer inspection                      $ 140.00
      BALANCE OWING                              $ 2,122.50     (PAID 10.10.2006 - RN.232722)
51.   Approval of these plans has been taken as a Notice of intention to commence works on the development.

52.   Dewatering - Council will allow discharge of the dewatering process to existing Council sewers which
      discharge to Pump Station NV2 in Mill Street providing rate of discharge does not impose any detrimental
      effects on the sewerage pump station. Council’s Sewerage Pump Station Foreman, Martin Pratt, Ph.
      5440 9136 shall be contacted to arrange appropriate monitoring of process.




AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@ac07b383\@[email protected]

Used in these records

About this file

File size
43 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED Decision Notice - 010.2006.00000159.001 [As Published].pdf · 43 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.