SPECIAL MEETING AGENDA 16 JULY 2020
Section 1.3 Effect
Update the date that this resolution will commence to have effect i.e. the commencement date of
the new planning scheme will be inserted when the new planning scheme takes effect.
Section 1.5 Interpretation
Update definitions as appropriate to better align with the Planning Act 2016, Planning Regulation
2017 and New Planning Scheme.
Section 9.6 Infrastructure charges taken to be a rate
Additional section informing that an infrastructure charge, for the purpose of recovery, is taken to
be “rates” of the local government and the recovery actions that may apply.
Section 9.7 Interest on overdue charges
Additional section informing that compound interest applies on overdue infrastructure charges.
Section 9.8 Goods and services tax
Additional section informing that GST does not apply to infrastructure charges.
Section 10.3 Allocation of levied charge to trunk infrastructure networks
Amend Table 10.2:
For Non-Residential development, amend allocations from Transport (85%) and Public parks
(15%) to Transport (100%) and Public parks (0%).
This is to align with the new planning scheme LGIP for the Public parks and land for
community facilities network’s Desired Standard of Service (DSS) where the “Land provision
target” and “Demand” only relates to population i.e. based on residential development only.
Remove Note # regarding applicability of the Stormwater component of the charge to
development only within the PIA as this is only required in the following Section 10.4.
Section 10.4 Schedule of Council Adopted Infrastructure Charges (under breakup agreement)
Amend Table 10.3 Schedule of Council adopted charges to:
reflect a similar layout to Schedule 16 of the Planning Regulation 2017 with charge rates
applicable to:
o The Noosa Plan 2006 (superseded planning scheme) development uses; and
o The Noosa Plan 2020 (new planning scheme) coinciding with Schedule 16 of the
Planning Regulation 2017 development uses;
provide additional transparency to include the basis, amounts and resulting percentage of
Council adopted charge reductions for those specified development uses. The charge rates
have been maintained to those previously adopted under Resolution No.4 for the current
2019-2020 financial year with the exception of Indoor sport and recreation “court area” where
the $1.29/m2 former “parks network” component reduction no longer applies.
Amend Note (3) to Network Reductions:
a) The Stormwater component of the charge is excluded for development located
outside the Coastal Area, Cooroy and Pomona PIA service catchments.
This is due to the new planning scheme LGIP that has changed the level of Stormwater
“trunk” infrastructure (i.e. increased the minimum “trunk” pipe diameter from 450mm to
650mm) with no trunk stormwater existing or currently planned for the Boreen Point,
Page 14 of 40
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.