36.9. The applicant’s Geotechnical engineer will be required to be on site for the whole of the
time during any excavation. The construction of the whole of the foundations is to be
supervised and directed on site by a consulting Geotechnical engineer. No work of any
such kind relating to the foundations shall be carried out if he is not on the site and
supervising and directing this work. Such works shall only be carried out during dry
weather conditions and if there is a risk of sand movement occurring, all work shall be
suspended until such steps, approved by the applicant’s Geotechnical engineer and the
Council’s Building Surveyor, have been taken to ensure that no further slippage will
result.
36.10.The builder, landscaper and all workers associated with construction of the works shall
at all times comply with the directions of the consulting geotechnical engineer.
36.11.The applicant shall take all necessary measures to ensure that the construction works
on the site will not have any adverse impact on the short-term and the long-term stability
of the sand dune formation or the stability of any adjoining property including buildings
and underground services. The applicant shall be responsible for any remedial works if
required on other properties as a consequence of the development works on the site.
36.12.Where the development works on the site requires the use (above ground or
underground) of other private properties, it is the applicant’s responsibility to negotiate
and arrange for any Permit to Enter these properties and any other related legal
requirements if needed prior to obtaining a Development Permit for Operational Works.
37. A verification survey of the building is to be carried out by a Licensed Surveyor and a
certificate lodged with Council at completion of the work confirming compliance with the
minimum required floor level and the maximum building height above natural surface, required
by the provisions of the Planning Scheme.
Additional Conditions
1. Deleted.
2. A qualified arborist shall be present on site to supervise works around the root zones of all
trees required to be retained. Prior to commencing any works safety fences shall be installed
around the trunks and as much of the root zone as possible to minimise the risk of compaction
and damage.
3. The rock wall adjacent to the decking of the swimming pool shall not exceed a maximum
height of 1.8 metres above the level of the decking.
4. Tree no. 47 shall be replaced with a suitable native species and located generally in the same
vicinity.
5. The proposed deck extension and all associated structures shall be setback a minimum of 2
metres from the northeastern side boundary. The setback shall be densely landscaped with
such landscaping to be in accordance with a revised landscaping plan which is required to be
submitted to Council for approval prior to the use commencing.
6. The undercroft areas of the swimming pool and deck shall be screened with landscaping with
such landscaping to be in accordance with an revised landscaping plan which is required to be
submitted to Council for approval prior to the use commencing.
5 REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Referral Trigger Referral Status Referral Agency Referral Address
Nil
Page 7 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Change to an Existing Approval - 010.2001.00210331.005 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 69 KB (small file)
- File type
No other editions are linked here.