PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA 10 DECEMBER 2019
Waste storage areas must provide for adequate separation of all reusable, recyclable
and waste materials. These must be located so that they are convenient and safe to
use.
The Plan must contain the following information:
a. The areas for the storage and separation of waste shown on a site plan;
b. A waste management table as indicated below is to be completed showing how
waste material is to be segregated - recycled – reused or disposed; and
c. Table – Waste Management Table
MATERIALS ON-SITE DESTINATION
Re-use and Recycling Disposal
Expected Estimated On-site Off-site *specify contractor
waste volume(m³) *specify proposed *specify contractor and landfill site or
materials re-use or on-site and recycling outlet other disposal site
recycling methods
Excavation
material
Green waste
Bricks
Concrete
Timber-please
specify
Plasterboard
Metals -
please specify
Asbestos
Other - please
specify
Note * If a demolition contractor is undertaking works, then the Waste Management
table is to be completed by the demolition contractor.
Damage to infrastructure
46. Any damage to footpaths, street plantings, natural vegetation/trees kerb and channel,
bridges or roadways must be repaired or reinstated to at least pre-existing conditions.
Vacant site
47. The site must be left clean and tidy free from debris such as concrete, wire, rubble,
brick/s and the like. If the site remains vacant for more than 30 days the lot/s must be
turfed or landscaped in accordance with Planning Scheme Policy PSP 3 –
Landscaping Plants and Guidelines and to the satisfaction of Council so as to not
cause nuisance to the surrounding area.
48. All waste materials must be removed from site.
Litter, erosion and sediment control
49. Litter, erosion and sediment control measures must be installed and maintained until
soils are stabilised by turf, vegetation or sealed.
Note: it is an offence under the Environmental Protection Act 1994 to deposit or
potentially allow litter, waste, soil, or other contaminants to enter a waterway or storm
water drainage system (e.g. roadside gutter).
Page 28 of 84
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.