93. High-flow bypass / first-flush capture design capacity must be designed to meet the
defined discharge criteria during a storm up to the 3 month ARI-6 minute design
rainfall event without surcharging or backing up the drainage system.
Submit Certification
94. Prior to the commencement of the use certification shall be provided to Council
demonstrating that the system has been installed in accordance with the above.
Noise
95. Mechanical plant and equipment, a/c units, motors, refrigeration equipment,
compressors, pumps etc. on site must be located within the building or suitably
provided with noise reduction measures and located to prevent a noise nuisance
beyond the boundary of the site and to not exceed the levels specified in Table 1.
Table 1
NOISE LIMITS AT A SENSITIVE RECEPTOR
PERIOD Noise level at noise sensitive place measured as the adjusted
maximum sound pressure level (Lamax, adj,T)
7am – 6pm Background noise level (LAbg,T) plus 5 dB(A)
6pm – 10pm Background noise level plus 5 dB(A)
10pm – 7am Inaudible
NOISE LEVELS AT COMMERCIAL PLACE
PERIOD Noise level at a commercial place measured as the adjusted
maximum sound pressure level (Lamax, adj,T)
7am – 6pm Background noise level (LAbg,T) plus 10 dB(A)
6pm – 10pm Background noise level plus10 dB(A)
10pm – 7am Background noise level plus 8 dB(A)
96. When requested by Council, a Noise Impact Assessment Report (NIAR) showing
monitoring and recording of noise levels must be undertaken to investigate any
complaint (other than a frivolous or vexatious complaint) caused by noise emissions
from operations at the premises.
97. Such monitoring must be undertaken within a reasonable and practicable timeframe
nominated by Council and be performed by a suitably qualified person in accordance
with accepted guidelines and standards. The report is to be submitted to Council
detailing the results of such monitoring and recommendations for any measures to
achieve compliance with limits outlined in Table 1 of this Decision Notice.
For the purpose of measuring and certifying relevant noise conditions and reporting
(e.g. mechanical plant and equipment, a/c units, motors, refrigeration equipment,
compressors, pumps, rooftop plant and equipment. etc) a suitably qualified person is
either:
a. a Registered Professional Engineer of Queensland, or
b. an environmental consultant with a minimum of three (3) years current
experience in the field of acoustics.
Page 35 of 84
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.